Source: Telangana Real Estate Regulatory Authority (TG-RERA), rera.telangana.gov.in. Reproduced as published; fetched 24/11/2026. The records compared above were read from 14/11/2026 to 24/11/2026. PropMap.ai reports what public records say. It is not legal advice.
Omsree Malabar Greens
Registration. The registration was valid until 04/06/2024, a date that has passed. TG-RERA listed no extension certificate when PropMap.ai read this project on 24/11/2026. Ask for: the extension order, or the occupancy certificate if the project is finished.
Worked out by PropMap.ai from the dates on this page.
Completion. The revised completion date the builder filed, 04/06/2024, has passed, and the project status on TG-RERA still reads "On-Going Project" (read 24/11/2026). Ask for: the occupancy certificate, or the revised completion date.
Worked out by PropMap.ai from the dates on this page.
Orders and complaints are not shown on this page. TG-RERA orders that name this project appear only in its Background Check report, after a compliance review, with the sources searched and their dates.
Drive times, places nearby and other projects within 5 km
Drive times
Approximate position: placed from the registered address, not the site itself. In our check 4 in 5 such positions were within about 2.5 km, and a few were over 5 km off.
Jeedimetla≈ 38 min at peak13 min without traffic
Kompally≈ 38 min at peak13 min without traffic
Secunderabad Junction≈ 40 min at peak13 min without traffic
All 42 places
Begumpet≈ 49 min at peak17 min without traffic
Lakdikapul≈ 51 min at peak
Documents
Documents uploaded
45 of 54 document slotsFiled with TG-RERA
Document groups on the record
3 (6 documents)Filed with TG-RERA
Pictures and plans held
0
Task-by-task progress, dated certificates and changes between reads
Declared progress as declared by the builder to TG-RERA, not inspected
No overall figure filed for the project. The record files 76 building tables and no project figure; each is shown as filed, in the record's order, and none is averaged. Read from TG-RERA on 24/11/2026.
Building table 180%
Building table 290%
Building table 380%
Building table 480%
Building table 580%
Building table 680%
Building table 780%
Building table 880%
Building table 980%
Building table 1080%
Building table 1180%
Building table 1280%
Building table 1380%
Building table 1480%
Building table 1580%
Building table 1680%
Building table 1780%
Building table 1880%
Building table 1980%
Building table 2080%
Building table 2180%
Building table 2258%
Building table 2380%
Building table 2480%
Building table 2580%
Building table 2680%
Building table 2780%
Building table 2880%
Building table 2980%
Building table 3080%
Building table 3180%
Building table 3280%
Building table 3380%
Building table 3451%
Building table 3580%
Building table 3655%
Building table 3780%
Building table 3880%
Building table 3980%
Building table 4080%
Building table 4180%
Building table 4280%
Building table 4380%
Building table 4480%
Building table 4558%
Building table 4680%
Building table 4780%
Building table 4880%
Building table 4980%
Building table 5080%
Building table 5159%
Building table 5280%
Building table 5351%
Building table 5480%
Building table 5580%
Building table 5680%
Building table 5780%
Building table 5880%
Building table 5980%
Building table 6080%
Building table 6180%
Building table 6280%
Building table 6380%
Building table 6480%
Building table 6580%
Building table 6670%
Building table 6780%
Building table 6880%
Building table 6970%
Building table 7080%
Building table 7180%
Building table 7280%
Building table 7380%
Building table 7480%
Building table 7570%
Building table 7670%
Source: TG-RERA project record, construction table (Tasks / Activity), a web record, not a signed certificate. Dates: the date PropMap.ai read the record; the table gives no as-of date. Percentage of work, as declared by the builder; the total it is measured against is not stated. Covers: 76 building tables, no project figure filed.
This filing's revised completion date is 04/06/2024: of 7 other filings under the same TG-RERA promoter record, 6 have a later date, 1 an earlier one and 0 the same, as last filed (records last updated 14/08/2025 to 04/05/2026).
Not counted on this page, so this is not a count of zero. TG-RERA orders that name a project appear only in that project's Background Check report, after a compliance review.
A passed date does not mean a project is late or unfinished: the filings rarely record completion.
As declared to TG-RERA. The filing gives counts, not which flat is free, so confirm any flat with the builder. Of 112 other projects in Alwal mandal with a booked count, 11 declare a larger share booked, 101 a smaller one and 0 the same, as last filed (records last updated 05/04/2019 to 11/11/2026; 1 carries no date).
76 units filed with TG-RERA without a bedroom type.
No price on record. PropMap.ai does not estimate prices. Type the builder's quote
What you type is kept on this device only and is not sent to PropMap.ai. PropMap.ai holds no price of its own: each figure below is an estimate from your quote and from the tax and duty rates listed with their sources.
Shamirpet (Genome Valley area)≈ 53 min at peak19 min without traffic
Panjagutta≈ 54 min at peak18 min without traffic
Ameerpet≈ 54 min at peak18 min without traffic
Abids≈ 55 min at peak19 min without traffic
Nampally station (Hyderabad Deccan)≈ 56 min at peak20 min without traffic
Koti≈ 58 min at peak20 min without traffic
Moosapet≈ 58 min at peak19 min without traffic
Kacheguda station≈ 58 min at peak20 min without traffic
Balanagar≈ 59 min at peak20 min without traffic
Mehdipatnam≈ 60 min at peak22 min without traffic
Banjara Hills≈ 63 min at peak21 min without traffic
Kukatpally≈ 65 min at peak23 min without traffic
LB Nagar≈ 66 min at peak25 min without traffic
Dilsukhnagar≈ 70 min at peak25 min without traffic
Pocharam (Infosys campus area)≈ 73 min at peak30 min without traffic
Jubilee Hills≈ 74 min at peak25 min without traffic
Miyapur≈ 76 min at peak28 min without traffic
Madhapur≈ 82 min at peak27 min without traffic
HITEC City≈ 82 min at peak28 min without traffic
Manikonda≈ 83 min at peak31 min without traffic
Raidurg (Mindspace)≈ 86 min at peak30 min without traffic
Shamshabad≈ 87 min at peak38 min without traffic
Khajaguda≈ 88 min at peak32 min without traffic
Lingampally≈ 88 min at peak33 min without traffic
Kondapur≈ 90 min at peak31 min without traffic
Patancheru≈ 90 min at peak38 min without traffic
Gachibowli≈ 90 min at peak33 min without traffic
Narsingi≈ 91 min at peak34 min without traffic
DLF Cyber City, Gachibowli≈ 92 min at peak33 min without traffic
Financial District≈ 95 min at peak35 min without traffic
Kokapet≈ 96 min at peak36 min without traffic
Tellapur≈ 97 min at peak46 min without traffic
Kollur≈ 100 min at peak48 min without traffic
Adibatla (Aerospace SEZ area)≈ 101 min at peak44 min without traffic
Nanakramguda (Waverock)≈ 101 min at peak38 min without traffic
Rajiv Gandhi International Airport≈ 110 min at peak43 min without traffic
How these are estimated
Peak: peak estimate: road-type speeds calibrated to TomTom Traffic Index 2025 for Hyderabad (about 15 km/h in the city); not live traffic, and a real rush hour can differ. Without traffic: free-flow estimate from OpenStreetMap roads (no traffic).
Chosen from public records by position, not ranked. Nobody can pay to appear here.
Filed documents and where each fact comes from
Filed by the builder on TG-RERA. Each link opens the copy held by the regulator, which may be slow or a scanned page. PropMap.ai links to these papers; it has not checked what they say.
RERA P02200000512 · by Om Sree Builders & Developers · YAPRAL, Alwal, 500087
Built by rule from this project's TG-RERA record, read by PropMap.ai on 24/11/2026. Figures are as the builder declared them. The marks and notes are the buyer's own.
Your marks stay on this device. What you mark, the date and your note are not sent to PropMap.ai or to anyone else, and they are lost if this browser's data is cleared. PropMap.ai counts that a mark was made on this project, never what it says. PropMap.ai arranges no visit and sends nothing to the builder.
11 items, none marked yet.
Ask the builder for
RegistrationRegistration ended on 04/06/2024
Ask for: the paper that extends the registration beyond that date, or the paper that certifies the project as complete.Question: “The registration has ended. Which paper extends it or closes it, and may I see it?” See the registration dates
Asked SeenDate: Note:
CompletionThe declared completion date (04/06/2024) has passed
Ask for: the new completion date in writing and, if it exists, the paper that allows people to move in.Question: “What is the new completion date, and has permission to occupy been given for my block?” See declared progress
Asked SeenDate: Note:
An approval paper is filed on TG-RERA; its number is not stated
Ask for: the approval number, and the approved plan that carries it.Question: “What is the approval number, and does the plan show my tower and my floor?” See approvals
Asked SeenDate: Note:
On recordThe builder declared 72 of 76 homes booked (record last updated 14/08/2025)
Ask for: the list of unsold homes of the type you want, with floor and facing.Question: “Which homes of my type are unsold today?” See the booked count
Asked SeenDate: Note:
PropMap.ai holds no prices
Ask for: the all-in cost in writing: the price, every other charge, taxes and registration costs, line by line.Question: “What is the total I will pay for this flat, with every charge and tax listed?”
Asked SeenDate: Note:
4 title files are uploaded to TG-RERA; PropMap.ai has not read them
Ask for: copies of the title papers for the land, for your lawyer to read. PropMap.ai does not check title: no flag found is not a clear title.Question: “May my lawyer have copies of the title papers, and of any loan or claim on the land?” See the filed title papers
Asked SeenDate: Note:
Look at on site (5)
On recordRERA number on record: P02200000512
Look at: the registration number printed on the site board, the brochure and any receipt.Question: “Is P02200000512 the number on everything you give me?”
Asked SeenDate: Note:
ConstructionThe filing shows 76 buildings
Look at: how many buildings stand, and the floor the structure has reached in yours. Take dated photos.Question: “Which floor has the structure reached in my tower?” See the filed buildings
Asked SeenDate: Note:
The filing lists 12 common facilities
Look at: which of them exist today, such as roads, water supply, drains and open space.Question: “Which shared facilities are finished, and when will the rest be?” See the filed facilities
Asked SeenDate: Note:
PropMap.ai's map position for this project is approximate
Look at: the exact entrance, and what stands on each side of the site.Question: “Is this the plot in the registration, and what is planned on the land next to it?” See the location
Asked SeenDate: Note:
Drive times on this page are estimates, not measured traffic
Look at: the drive to your daily destination, timed by you at the hour you would travel.Question: “Which road do residents take at peak hour?” See the estimates
Asked SeenDate: Note:
Is this home right for you? Four questions, kept on this device
Is this home right for you?
Answer four questions once, and each project says in words which of your needs its record meets. Kept on this device only.
45
3 slabs filed
463 slabs filed
473 slabs filed
483 slabs filed
493 slabs filed
503 slabs filed
513 slabs filed
523 slabs filed
533 slabs filed
543 slabs filed
553 slabs filed
563 slabs filed
723 slabs filed
733 slabs filed
743 slabs filed
753 slabs filed
763 slabs filed
773 slabs filed
783 slabs filed
793 slabs filed
803 slabs filed
73 slabs filed
83 slabs filed
93 slabs filed
103 slabs filed
113 slabs filed
123 slabs filed
133 slabs filed
143 slabs filed
153 slabs filed
303 slabs filed
313 slabs filed
323 slabs filed
333 slabs filed
343 slabs filed
353 slabs filed
363 slabs filed
373 slabs filed
383 slabs filed
393 slabs filed
403 slabs filed
413 slabs filed
423 slabs filed
583 slabs filed
593 slabs filed
603 slabs filed
613 slabs filed
623 slabs filed
633 slabs filed
643 slabs filed
653 slabs filed
663 slabs filed
673 slabs filed
573 slabs filed
163 slabs filed
433 slabs filed
833 slabs filed
703 slabs filed
The site: land, built-up area, survey number
Land
9.25 acres
Net of road and water setbacks
5.42 acres
Approved built-up area
3,41,657 sq ft
Buildings on the approved plan
76
Towers with homes
76
Lost to road widening or a lake's full tank level
1,66,487 sq ft
Survey number
233,234,235,236
Site boundaries
east
ROAD
west
ROAD
north
(name withheld)
south
ROAD
Filed with TG-RERA. People's names are withheld.
Common facilities filed with TG-RERA (15)
Internal Roads & Footpaths100% declared
Water Supply100% declared
Sewerage (Chamber, Lines, Septic Tank , STP)100% declared
Storm Water Drains100% declared
Green Strip/TOT LOT/Park100% declared
Street Lighting100% declared
Community Buildings100% declared
Treatment And Disposal Of Sewage And Sullage Water100% declared
Solid Waste Management And DisposalNot provided
Water Conservation, Rain water Harvesting100% declared
Energy managementNot provided
Fire Protection And Fire Safety RequirementsNot provided
Electrical Meter Room, Sub-Station, Receiving Station100% declared
Aggregate area of recreational Open Space100% declared
Places around this project are not counted yet: locusPro, the location record PropMap.ai uses, covers West Hyderabad only so far. The map shows the project's position only.