Not present in the filingwork declared by the builder
Filed update 28/07/2025 · read 14/11/2026 · See filing >
What the record shows
Registered now. As published on TG-RERA. TG-RERA record read on 14/11/2026.
Findings from the TG-RERA record
Worked out by PropMap.ai's rules from the dates and figures filed, read 14/11/2026.
Construction. All 8 facilities this layout's filing lists show 0% done, figures that may never have been entered, in a record last updated 28/07/2025. The completion date filed is 30/11/2026, 1 day away. PropMap.ai cannot tell whether work has not started or the figures were left blank. Ask for: the latest dated progress certificate.
Registration status
Registration number
P01900009888Filed with TG-RERA
Registered on
27/07/2024Filed with TG-RERA
Valid until
30/11/2026, extended (first certificate to 26/07/2026)Filed with TG-RERA
Extensions
At least 1, the latest valid until 30/11/2026Filed with TG-RERA
Source: Telangana Real Estate Regulatory Authority (TG-RERA), rera.telangana.gov.in. Reproduced as published; fetched 14/11/2026. PropMap.ai reports what public records say. It is not legal advice.
read 14/11/2026 · figures as declared by the builder, not checked on site
Worked out by PropMap.ai from the declared work, the dates and the last-updated date on this page. It does not say the work is delayed.
Orders and complaints are not shown on this page. TG-RERA orders that name this project appear only in its Background Check report, after a compliance review, with the sources searched and their dates.
Progress
Declared progress
Not present in the filing
Last updated on TG-RERA
28/07/2025Filed with TG-RERA
Actual completion
Not present in the filing
Occupancy certificate
Not present in the filing
Task-by-task progress, dated certificates and changes between reads
Declared progress
Not found on TG-RERA. Ask the builder for the latest quarterly progress report filed with TG-RERA (Forms 1, 2 and 3).
No change between PropMap.ai's reads of 05/11/2026 and 14/11/2026 in the registration dates, completion date or declared work.
Past the proposed completion date, not shown as completed
0
Shown as completed
0
TG-RERA complaint orders
Not counted
Not counted on this page, so this is not a count of zero. TG-RERA orders that name a project appear only in that project's Background Check report, after a compliance review.
A passed date does not mean a project is late or unfinished: the filings rarely record completion.
As declared to TG-RERA, and booking figures may lag.
No price on record. PropMap.ai does not estimate prices. Type the builder's quote
What you type is kept on this device only and is not sent to PropMap.ai. PropMap.ai holds no price of its own: each figure below is an estimate from your quote and from the tax and duty rates listed with their sources.
Filed by the builder on TG-RERA. Each link opens the copy held by the regulator, which may be slow or a scanned page. PropMap.ai links to these papers; it has not checked what they say.
RERA P01900009888 · by Ramreddy Saidulubabu · SINGARNENI PALLE VILLAGE, MAMILLAGUDEM GRAM PANCHAYATH, MOTHEY MANDAL, Mamillagudem, Mothey, 508212
Built by rule from this project's TG-RERA record, read by PropMap.ai on 14/11/2026. Figures are as the builder declared them. The marks and notes are the buyer's own.
Your marks stay on this device. What you mark, the date and your note are not sent to PropMap.ai or to anyone else, and they are lost if this browser's data is cleared. PropMap.ai counts that a mark was made on this project, never what it says. PropMap.ai arranges no visit and sends nothing to the builder.
8 items, none marked yet.
Ask the builder for
ConstructionThe record shows 0% for every facility near the declared completion date
Ask for: the latest dated certificate of work done, signed by the project's architect or engineer. The record may be out of date: PropMap.ai cannot tell.Question: “How much of the work is done today, who certified it, and on what date?” See the two figures and the record's date
Asked SeenDate: Note:
On recordRegistration is current until 30/11/2026
Ask for: the possession date, written into the draft of your agreement.Question: “Does the possession date in my agreement fall before 30/11/2026, when the registration ends?” See the registration dates
Asked SeenDate: Note:
PropMap.ai holds no prices
Ask for: the all-in cost in writing: the price, every other charge, taxes and registration costs, line by line.Question: “What is the total I will pay for this flat, with every charge and tax listed?”
Asked SeenDate: Note:
6 title files are uploaded to TG-RERA; PropMap.ai has not read them
Ask for: copies of the title papers for the land, for your lawyer to read. PropMap.ai does not check title: no flag found is not a clear title.Question: “May my lawyer have copies of the title papers, and of any loan or claim on the land?” See the filed title papers
Asked SeenDate: Note:
Look at on site (4)
On recordRERA number on record: P01900009888
Look at: the registration number printed on the site board, the brochure and any receipt.Question: “Is P01900009888 the number on everything you give me?”
Asked SeenDate: Note:
The filing lists 8 common facilities
Look at: which of them exist today, such as roads, water supply, drains and open space.Question: “Which shared facilities are finished, and when will the rest be?” See the filed facilities
Asked SeenDate: Note:
On recordA registered address is on record
Look at: that the site you are shown is at the registered address, and what stands on each side of it.Question: “Is this the plot in the registration, and what is planned on the land next to it?” See the registered address
Asked SeenDate: Note:
PropMap.ai holds no drive time for this project
Look at: the drive to your daily destination, timed by you at the hour you would travel.Question: “Which road do residents take at peak hour?”
Asked SeenDate: Note:
Is this home right for you? Four questions, kept on this device
Is this home right for you?
Answer four questions once, and each project says in words which of your needs its record meets. Kept on this device only.
Fire Protection And Fire Safety Requirements
Not provided
Electrical Meter Room, Sub-Station, Receiving Station0% declared
Aggregate area of recreational Open SpaceNot provided
Labels: Filed with TG-RERA (the builder's filing or the regulator's record), Builder's site says, Measured from open map data, Conflict, Not known. A filing and the builder's own site agreeing does not prove a figure: both come from the builder.
Project location Exact location
Places around this project are not counted yet: locusPro, the location record PropMap.ai uses, covers West Hyderabad only so far. The map shows the project's position only.