Registration ended. TG-RERA record read on 14/11/2026.
Findings from the TG-RERA record
Worked out by PropMap.ai's rules from the dates and figures filed, read 14/11/2026.
Registration. The registration was valid until 25/02/2024, a date that has passed. TG-RERA listed no extension certificate when PropMap.ai read this project on 14/11/2026. Ask for: the extension order, or the occupancy certificate if the project is finished.
Worked out by PropMap.ai from the dates on this page.
Plans
3 held
All 3 plans
Pictures and plans 1
From the builder's website. Pictures may be artist's impressions.
Plans filed with TG-RERA 2
Filed with TG-RERA by the builder, as uploaded. People's names are covered. Not checked by PropMap.ai.
Source: Telangana Real Estate Regulatory Authority (TG-RERA), rera.telangana.gov.in. Reproduced as published; fetched 14/11/2026. The records compared above were read on 14/11/2026. PropMap.ai reports what public records say. It is not legal advice.
Empire Capetown
Completion. The completion date the builder first filed, 25/02/2024, has passed, and the project status on TG-RERA still reads "New Project" (read 14/11/2026). Ask for: the occupancy certificate, or the revised completion date.
Worked out by PropMap.ai from the dates on this page.
Orders and complaints are not shown on this page. TG-RERA orders that name this project appear only in its Background Check report, after a compliance review, with the sources searched and their dates.
Declared progress
Not present in the filing
Last updated on TG-RERA
26/05/2025Filed with TG-RERA
Actual completion
Not present in the filing
Occupancy certificate
Not present in the filing
Task-by-task progress, dated certificates and changes between reads
Declared progress
Not found on TG-RERA. Ask the builder for the latest quarterly progress report filed with TG-RERA (Forms 1, 2 and 3).
This filing's proposed completion date is 25/02/2024: of 3 other filings under the same TG-RERA promoter record, 3 have a later date, 0 an earlier one and 0 the same, as last filed (records last updated 26/05/2025 to 27/06/2026).
No change between PropMap.ai's reads of 05/11/2026 and 14/11/2026 in the registration dates, completion date or declared work.
Not counted on this page, so this is not a count of zero. TG-RERA orders that name a project appear only in that project's Background Check report, after a compliance review.
A passed date does not mean a project is late or unfinished: the filings rarely record completion.
The counts in this filing did not look believable, so PropMap.ai does not show them. Ask the builder for the numbers in writing.
No price on record. PropMap.ai does not estimate prices. Type the builder's quote
What you type is kept on this device only and is not sent to PropMap.ai. PropMap.ai holds no price of its own: each figure below is an estimate from your quote and from the tax and duty rates listed with their sources.
Raidurg (Mindspace)≈ 72 min at peak35 min without traffic
Gachibowli≈ 72 min at peak32 min without traffic
Khajaguda≈ 72 min at peak34 min without traffic
DLF Cyber City, Gachibowli≈ 72 min at peak32 min without traffic
Nanakramguda (Waverock)≈ 73 min at peak34 min without traffic
Kondapur≈ 75 min at peak32 min without traffic
HITEC City≈ 76 min at peak34 min without traffic
Narsingi≈ 77 min at peak35 min without traffic
Kukatpally≈ 81 min at peak33 min without traffic
Manikonda≈ 82 min at peak38 min without traffic
Madhapur≈ 83 min at peak36 min without traffic
Balanagar≈ 86 min at peak36 min without traffic
Shamirpet (Genome Valley area)≈ 86 min at peak44 min without traffic
Kompally≈ 86 min at peak41 min without traffic
Shamshabad≈ 87 min at peak44 min without traffic
Moosapet≈ 87 min at peak36 min without traffic
Jubilee Hills≈ 89 min at peak38 min without traffic
Mehdipatnam≈ 91 min at peak42 min without traffic
Jeedimetla≈ 93 min at peak43 min without traffic
Ameerpet≈ 99 min at peak42 min without traffic
Panjagutta≈ 100 min at peak42 min without traffic
Banjara Hills≈ 100 min at peak42 min without traffic
Lakdikapul≈ 100 min at peak45 min without traffic
Rajiv Gandhi International Airport≈ 105 min at peak50 min without traffic
Nampally station (Hyderabad Deccan)≈ 106 min at peak48 min without traffic
Begumpet≈ 107 min at peak44 min without traffic
Abids≈ 108 min at peak48 min without traffic
Koti≈ 110 min at peak49 min without traffic
Pocharam (Infosys campus area)≈ 115 min at peak62 min without traffic
Kacheguda station≈ 116 min at peak50 min without traffic
Secunderabad Junction≈ 116 min at peak47 min without traffic
Adibatla (Aerospace SEZ area)≈ 120 min at peak62 min without traffic
Dilsukhnagar≈ 122 min at peak54 min without traffic
Uppal≈ 127 min at peak54 min without traffic
LB Nagar≈ 129 min at peak59 min without traffic
How these are estimated
Peak: peak estimate: road-type speeds calibrated to TomTom Traffic Index 2025 for Hyderabad (about 15 km/h in the city); not live traffic, and a real rush hour can differ. Without traffic: free-flow estimate from OpenStreetMap roads (no traffic).
Chosen from public records by position, not ranked. Nobody can pay to appear here.
Filed documents and where each fact comes from
Filed by the builder on TG-RERA. Each link opens the copy held by the regulator, which may be slow or a scanned page. PropMap.ai links to these papers; it has not checked what they say.
RERA P01100003334 · by Empire Delta Projects LLP · MUMBAI HIGHWAY, OPP ZPH SCHOOL, KANDI, 502285
Built by rule from this project's TG-RERA record, read by PropMap.ai on 14/11/2026. Figures are as the builder declared them. The marks and notes are the buyer's own.
Your marks stay on this device. What you mark, the date and your note are not sent to PropMap.ai or to anyone else, and they are lost if this browser's data is cleared. PropMap.ai counts that a mark was made on this project, never what it says. PropMap.ai arranges no visit and sends nothing to the builder.
8 items, none marked yet.
Ask the builder for
RegistrationRegistration ended on 25/02/2024
Ask for: the paper that extends the registration beyond that date, or the paper that certifies the project as complete.Question: “The registration has ended. Which paper extends it or closes it, and may I see it?” See the registration dates
Asked SeenDate: Note:
CompletionThe declared completion date (25/02/2024) has passed
Ask for: the new completion date in writing and, if it exists, the paper that allows people to move in.Question: “What is the new completion date, and has permission to occupy been given for my block?” See declared progress
Asked SeenDate: Note:
PropMap.ai holds no prices
Ask for: the all-in cost in writing: the price, every other charge, taxes and registration costs, line by line.Question: “What is the total I will pay for this flat, with every charge and tax listed?”
Asked SeenDate: Note:
3 title files are uploaded to TG-RERA; PropMap.ai has not read them
Ask for: copies of the title papers for the land, for your lawyer to read. PropMap.ai does not check title: no flag found is not a clear title.Question: “May my lawyer have copies of the title papers, and of any loan or claim on the land?” See the filed title papers
Asked SeenDate: Note:
Look at on site (4)
On recordRERA number on record: P01100003334
Look at: the registration number printed on the site board, the brochure and any receipt.Question: “Is P01100003334 the number on everything you give me?”
Asked SeenDate: Note:
The filing lists 7 common facilities
Look at: which of them exist today, such as roads, water supply, drains and open space.Question: “Which shared facilities are finished, and when will the rest be?” See the filed facilities
Asked SeenDate: Note:
On recordA registered address is on record
Look at: that the site you are shown is at the registered address, and what stands on each side of it.Question: “Is this the plot in the registration, and what is planned on the land next to it?” See the registered address
Asked SeenDate: Note:
Drive times on this page are estimates, not measured traffic
Look at: the drive to your daily destination, timed by you at the hour you would travel.Question: “Which road do residents take at peak hour?” See the estimates
Asked SeenDate: Note:
Is this home right for you? Four questions, kept on this device
Is this home right for you?
Answer four questions once, and each project says in words which of your needs its record meets. Kept on this device only.
Labels: Filed with TG-RERA (the builder's filing or the regulator's record), Builder's site says, Measured from open map data, Conflict, Not known. A filing and the builder's own site agreeing does not prove a figure: both come from the builder.
Project location Exact location
Places around this project are not counted yet: locusPro, the location record PropMap.ai uses, covers West Hyderabad only so far. The map shows the project's position only.