Left blank in the filingwork declared by the builder, 2 building tables
Building table 190%
Building table 286%
Filed update 03/07/2022 · read 14/11/2026 · See filing >
What the record shows
Registration ended. TG-RERA record read on 14/11/2026.
Findings from the TG-RERA record
Worked out by PropMap.ai's rules from the dates and figures filed, read 14/11/2026.
Registration. The registration was valid until 22/01/2026, a date that has passed. TG-RERA listed no extension certificate when PropMap.ai read this project on 14/11/2026. Ask for: the extension order, or the occupancy certificate if the project is finished.
Source: Telangana Real Estate Regulatory Authority (TG-RERA), rera.telangana.gov.in. Reproduced as published; fetched 14/11/2026. The records compared above were read from 14/11/2026 to 24/11/2026. PropMap.ai reports what public records say. It is not legal advice.
Galaxy Towers
Worked out by PropMap.ai from the dates on this page.
Completion. The completion date the builder first filed, 22/01/2026, has passed, and the project status on TG-RERA still reads "New Project" (read 14/11/2026). Ask for: the occupancy certificate, or the revised completion date.
Worked out by PropMap.ai from the dates on this page.
Orders and complaints are not shown on this page. TG-RERA orders that name this project appear only in its Background Check report, after a compliance review, with the sources searched and their dates.
SY NO.22, POCHARAM, Ghatkesar, 500088Filed with TG-RERA
Mandal, district
Ghatkesar, Medchal-MalkajgiriFiled with TG-RERA
Map position
Exact: the TG-RERA portal's map pinFiled with TG-RERA
Drive times, places nearby and other projects within 5 km
Drive times
Pocharam (Infosys campus area)≈ 11 min at peak5 min without traffic
Uppal≈ 36 min at peak17 min without traffic
Shamirpet (Genome Valley area)≈ 45 min at peak25 min without traffic
All 42 places
LB Nagar≈ 49 min at peak23 min without traffic
Dilsukhnagar≈ 56 min at peak25 min without traffic
Documents
Documents uploaded
27 of 32 document slotsFiled with TG-RERA
Document groups on the record
4 (9 documents)Filed with TG-RERA
Pictures and plans held
0
Task-by-task progress, dated certificates and changes between reads
Declared progress as declared by the builder to TG-RERA, not inspected
No overall figure filed for the project. The record files 2 building tables and no project figure; each is shown as filed, in the record's order, and none is averaged. Read from TG-RERA on 14/11/2026.
Building table 190%
Building table 286%
Source: TG-RERA project record, construction table (Tasks / Activity), a web record, not a signed certificate. Dates: the date PropMap.ai read the record; the table gives no as-of date. Percentage of work, as declared by the builder; the total it is measured against is not stated. Covers: 2 building tables, no project figure filed.
No change between PropMap.ai's reads of 05/11/2026 and 14/11/2026 in the registration dates, completion date or declared work (88%).
Not counted on this page, so this is not a count of zero. TG-RERA orders that name a project appear only in that project's Background Check report, after a compliance review.
A passed date does not mean a project is late or unfinished: the filings rarely record completion.
Declared by the builder to TG-RERA, not checked against those projects.
Homes
Homes, total
96Filed with TG-RERA
Booked, as declared
0Filed with TG-RERA
Home types and sizes
Not present in the filing
Types, sizes, bookings and the cost calculator
0 of 96 booked
As declared to TG-RERA. The filing gives counts, not which flat is free, so confirm any flat with the builder. Of 61 other projects in Ghatkesar mandal with a booked count, 12 declare a larger share booked, 0 a smaller one and 49 the same, as last filed (records last updated 20/07/2019 to 22/10/2026).
96 units filed with TG-RERA without a bedroom type.
No price on record. PropMap.ai does not estimate prices. Type the builder's quote
What you type is kept on this device only and is not sent to PropMap.ai. PropMap.ai holds no price of its own: each figure below is an estimate from your quote and from the tax and duty rates listed with their sources.
Adibatla (Aerospace SEZ area)≈ 61 min at peak34 min without traffic
Secunderabad Junction≈ 61 min at peak25 min without traffic
Kompally≈ 63 min at peak35 min without traffic
Abids≈ 63 min at peak28 min without traffic
Nampally station (Hyderabad Deccan)≈ 63 min at peak29 min without traffic
Lakdikapul≈ 64 min at peak29 min without traffic
Jeedimetla≈ 70 min at peak36 min without traffic
Panjagutta≈ 72 min at peak32 min without traffic
Mehdipatnam≈ 74 min at peak33 min without traffic
Ameerpet≈ 76 min at peak32 min without traffic
Begumpet≈ 77 min at peak31 min without traffic
Banjara Hills≈ 78 min at peak34 min without traffic
Shamshabad≈ 79 min at peak45 min without traffic
Patancheru≈ 84 min at peak51 min without traffic
Rajiv Gandhi International Airport≈ 84 min at peak45 min without traffic
Moosapet≈ 85 min at peak36 min without traffic
Balanagar≈ 87 min at peak37 min without traffic
Miyapur≈ 91 min at peak44 min without traffic
Tellapur≈ 91 min at peak55 min without traffic
Jubilee Hills≈ 92 min at peak39 min without traffic
Kukatpally≈ 92 min at peak40 min without traffic
Kollur≈ 94 min at peak57 min without traffic
Narsingi≈ 95 min at peak44 min without traffic
Kokapet≈ 96 min at peak46 min without traffic
Manikonda≈ 97 min at peak42 min without traffic
Raidurg (Mindspace)≈ 98 min at peak42 min without traffic
Khajaguda≈ 98 min at peak43 min without traffic
Gachibowli≈ 98 min at peak43 min without traffic
DLF Cyber City, Gachibowli≈ 98 min at peak44 min without traffic
Financial District≈ 98 min at peak46 min without traffic
Madhapur≈ 99 min at peak41 min without traffic
Lingampally≈ 100 min at peak50 min without traffic
Kondapur≈ 101 min at peak45 min without traffic
Nanakramguda (Waverock)≈ 102 min at peak49 min without traffic
HITEC City≈ 102 min at peak43 min without traffic
How these are estimated
Peak: peak estimate: road-type speeds calibrated to TomTom Traffic Index 2025 for Hyderabad (about 15 km/h in the city); not live traffic, and a real rush hour can differ. Without traffic: free-flow estimate from OpenStreetMap roads (no traffic).
Chosen from public records by position, not ranked. Nobody can pay to appear here.
Filed documents and where each fact comes from
Filed by the builder on TG-RERA. Each link opens the copy held by the regulator, which may be slow or a scanned page. PropMap.ai links to these papers; it has not checked what they say.
RERA P02200002256 · by Surya Constructions · SY NO.22, POCHARAM, Ghatkesar, 500088
Built by rule from this project's TG-RERA record, read by PropMap.ai on 14/11/2026. Figures are as the builder declared them. The marks and notes are the buyer's own.
Your marks stay on this device. What you mark, the date and your note are not sent to PropMap.ai or to anyone else, and they are lost if this browser's data is cleared. PropMap.ai counts that a mark was made on this project, never what it says. PropMap.ai arranges no visit and sends nothing to the builder.
12 items, none marked yet.
Ask the builder for
RegistrationRegistration ended on 22/01/2026
Ask for: the paper that extends the registration beyond that date, or the paper that certifies the project as complete.Question: “The registration has ended. Which paper extends it or closes it, and may I see it?” See the registration dates
Asked SeenDate: Note:
CompletionThe declared completion date (22/01/2026) has passed
Ask for: the new completion date in writing and, if it exists, the paper that allows people to move in.Question: “What is the new completion date, and has permission to occupy been given for my block?” See declared progress
Asked SeenDate: Note:
On recordApproval number 022439/GHT/R1/U6/HMD is declared to TG-RERA
Ask for: the approved plan that carries this number, showing your tower and floor.Question: “Does the approved plan with this number show my tower, my floor and the flat as offered?” See approvals
Asked SeenDate: Note:
On recordThe builder declared 0 of 96 homes booked (record last updated 03/07/2022)
Ask for: the list of unsold homes of the type you want, with floor and facing.Question: “Which homes of my type are unsold today?” See the booked count
Asked SeenDate: Note:
PropMap.ai holds no prices
Ask for: the all-in cost in writing: the price, every other charge, taxes and registration costs, line by line.Question: “What is the total I will pay for this flat, with every charge and tax listed?”
Asked SeenDate: Note:
2 title files are uploaded to TG-RERA; PropMap.ai has not read them
Ask for: copies of the title papers for the land, for your lawyer to read. PropMap.ai does not check title: no flag found is not a clear title.Question: “May my lawyer have copies of the title papers, and of any loan or claim on the land?” See the filed title papers
Asked SeenDate: Note:
Look at on site (6)
On recordRERA number on record: P02200002256
Look at: the registration number printed on the site board, the brochure and any receipt.Question: “Is P02200002256 the number on everything you give me?”
Asked SeenDate: Note:
ConstructionThe filing shows 2 buildings
Look at: how many buildings stand, and the floor the structure has reached in yours. Take dated photos.Question: “Which floor has the structure reached in my tower?” See the filed buildings
Asked SeenDate: Note:
ConstructionThe builder declared 88% of work (record last updated 03/07/2022)
Look at: whether what stands looks like that share of the work: structure, outside finish, lifts and fittings.Question: “What work is going on this month, and what is left before handover?” See declared progress
Asked SeenDate: Note:
The filing lists 9 common facilities
Look at: which of them exist today, such as roads, water supply, drains and open space.Question: “Which shared facilities are finished, and when will the rest be?” See the filed facilities
Asked SeenDate: Note:
On recordA registered address is on record
Look at: that the site you are shown is at the registered address, and what stands on each side of it.Question: “Is this the plot in the registration, and what is planned on the land next to it?” See the registered address
Asked SeenDate: Note:
Drive times on this page are estimates, not measured traffic
Look at: the drive to your daily destination, timed by you at the hour you would travel.Question: “Which road do residents take at peak hour?” See the estimates
Asked SeenDate: Note:
Is this home right for you? Four questions, kept on this device
Is this home right for you?
Answer four questions once, and each project says in words which of your needs its record meets. Kept on this device only.
Sewerage (Chamber, Lines, Septic Tank , STP)
0% declared
Storm Water Drains0% declared
Green Strip/TOT LOT/Park0% declared
Street Lighting0% declared
Community BuildingsNot provided
Treatment And Disposal Of Sewage And Sullage WaterNot stated
Solid Waste Management And DisposalNot provided
Water Conservation, Rain water HarvestingNot stated
Energy managementNot provided
Fire Protection And Fire Safety RequirementsNot provided
Electrical Meter Room, Sub-Station, Receiving StationNot stated
Aggregate area of recreational Open SpaceNot stated
Labels: Filed with TG-RERA (the builder's filing or the regulator's record), Builder's site says, Measured from open map data, Conflict, Not known. A filing and the builder's own site agreeing does not prove a figure: both come from the builder.
Project location Exact location
Places around this project are not counted yet: locusPro, the location record PropMap.ai uses, covers West Hyderabad only so far. The map shows the project's position only.