Source: Telangana Real Estate Regulatory Authority (TG-RERA), rera.telangana.gov.in. Reproduced as published; fetched 14/11/2026. The records compared above were read from 14/11/2026 to 24/11/2026. PropMap.ai reports what public records say. It is not legal advice.
Mypi Villas Constructions Phase2
Registration. The registration was valid until 01/06/2025, a date that has passed. TG-RERA listed no extension certificate when PropMap.ai read this project on 14/11/2026. Ask for: the extension order, or the occupancy certificate if the project is finished.
Worked out by PropMap.ai from the dates on this page.
Completion. The completion date the builder first filed, 01/06/2025, has passed, and the project status on TG-RERA still reads "New Project" (read 14/11/2026). Ask for: the occupancy certificate, or the revised completion date.
Worked out by PropMap.ai from the dates on this page.
Orders and complaints are not shown on this page. TG-RERA orders that name this project appear only in its Background Check report, after a compliance review, with the sources searched and their dates.
Progress
Declared progress
Left blank in the filing
Last updated on TG-RERA
28/02/2020Filed with TG-RERA
Actual completion
Not present in the filing
Occupancy certificate
Not present in the filing
Location
Registered address
SY NO 53P NH44, OPP GVK EMRI, Gundlapochampally, Medchal, 501401Filed with TG-RERA
Mandal, district
Medchal, Medchal-MalkajgiriFiled with TG-RERA
Map position
Exact: the TG-RERA portal's map pinFiled with TG-RERA
Drive times, places nearby and other projects within 5 km
Drive times
Kompally≈ 16 min at peak7 min without traffic
Jeedimetla≈ 23 min at peak10 min without traffic
Shamirpet (Genome Valley area)≈ 26 min at peak14 min without traffic
All 42 places
Patancheru≈ 46 min at peak28 min without traffic
Secunderabad Junction≈ 48 min at peak21 min without traffic
Documents
Documents uploaded
9 of 17 document slotsFiled with TG-RERA
Document groups on the record
3 (7 documents)Filed with TG-RERA
Pictures and plans held
2
Task-by-task progress, dated certificates and changes between reads
Declared progress as declared by the builder to TG-RERA, not inspected
No overall figure filed for the project. The record files 51 building tables and no project figure; each is shown as filed, in the record's order, and none is averaged. Read from TG-RERA on 14/11/2026.
Building table 10%
Building table 29%
Building table 39%
Building table 49%
Building table 59%
Building table 69%
Building table 79%
Building table 89%
Building table 99%
Building table 1015%
Building table 1122%
Building table 1224%
Building table 1322%
Building table 149%
Building table 159%
Building table 169%
Building table 179%
Building table 1819%
Building table 1915%
Building table 2019%
Building table 2119%
Building table 2227%
Building table 2319%
Building table 2419%
Building table 2525%
Building table 2619%
Building table 2715%
Building table 2819%
Building table 2924%
Building table 3025%
Building table 319%
Building table 3219%
Building table 3325%
Building table 3419%
Building table 3526%
Building table 3620%
Building table 3720%
Building table 3820%
Building table 3925%
Building table 4018%
Building table 418%
Building table 428%
Building table 439%
Building table 448%
Building table 459%
Building table 4627%
Building table 4731%
Building table 4829%
Building table 490%
Building table 5029%
Building table 510%
Source: TG-RERA project record, construction table (Tasks / Activity), a web record, not a signed certificate. Dates: the date PropMap.ai read the record; the table gives no as-of date. Percentage of work, as declared by the builder; the total it is measured against is not stated. Covers: 51 building tables, no project figure filed.
No change between PropMap.ai's reads of 05/11/2026 and 14/11/2026 in the registration dates, completion date or declared work (16%).
Not counted on this page, so this is not a count of zero. TG-RERA orders that name a project appear only in that project's Background Check report, after a compliance review.
A passed date does not mean a project is late or unfinished: the filings rarely record completion.
Declared by the builder to TG-RERA, not checked against those projects.
Homes
Homes, total
103Filed with TG-RERA
Booked, as declared
0Filed with TG-RERA
Home types and sizes
3 BHK · 3,942 sq ftFiled with TG-RERA
Types, sizes, bookings and the cost calculator
0 of 103 booked
As declared to TG-RERA. The filing gives counts, not which flat is free, so confirm any flat with the builder. Of 108 other projects in Medchal mandal with a booked count, 28 declare a larger share booked, 0 a smaller one and 80 the same, as last filed (records last updated 27/06/2019 to 30/10/2026).
Home types
Type
Homes
Not booked
Saleable size
3 BHK
5
5
3,942 sq ft
Saleable area, not carpet area. Ask for the carpet area in writing. 98 other units are filed without a bedroom type, such as clubhouses or shops.
No price on record. PropMap.ai does not estimate prices. Type the builder's quote
What you type is kept on this device only and is not sent to PropMap.ai. PropMap.ai holds no price of its own: each figure below is an estimate from your quote and from the tax and duty rates listed with their sources.
Towers, floor by floor (51)
booked not booked, as declared.
149 APARTMENT BLOCK5 floors with homes · 6 slabs filed · 5 homes, 0 booked
Pocharam (Infosys campus area)≈ 54 min at peak33 min without traffic
Kukatpally≈ 55 min at peak23 min without traffic
Panjagutta≈ 56 min at peak23 min without traffic
Kollur≈ 57 min at peak33 min without traffic
Abids≈ 58 min at peak26 min without traffic
Nampally station (Hyderabad Deccan)≈ 59 min at peak27 min without traffic
Koti≈ 61 min at peak27 min without traffic
Lingampally≈ 63 min at peak30 min without traffic
Mehdipatnam≈ 63 min at peak29 min without traffic
Kacheguda station≈ 63 min at peak27 min without traffic
Banjara Hills≈ 66 min at peak27 min without traffic
Uppal≈ 67 min at peak28 min without traffic
Financial District≈ 69 min at peak35 min without traffic
Kondapur≈ 69 min at peak30 min without traffic
Kokapet≈ 69 min at peak38 min without traffic
Raidurg (Mindspace)≈ 70 min at peak30 min without traffic
Gachibowli≈ 70 min at peak33 min without traffic
Khajaguda≈ 70 min at peak35 min without traffic
DLF Cyber City, Gachibowli≈ 70 min at peak32 min without traffic
HITEC City≈ 70 min at peak29 min without traffic
Nanakramguda (Waverock)≈ 71 min at peak38 min without traffic
Jubilee Hills≈ 73 min at peak29 min without traffic
Dilsukhnagar≈ 74 min at peak32 min without traffic
Narsingi≈ 75 min at peak38 min without traffic
Madhapur≈ 78 min at peak31 min without traffic
Manikonda≈ 80 min at peak37 min without traffic
LB Nagar≈ 81 min at peak35 min without traffic
Adibatla (Aerospace SEZ area)≈ 83 min at peak49 min without traffic
Shamshabad≈ 85 min at peak45 min without traffic
Rajiv Gandhi International Airport≈ 103 min at peak50 min without traffic
How these are estimated
Peak: peak estimate: road-type speeds calibrated to TomTom Traffic Index 2025 for Hyderabad (about 15 km/h in the city); not live traffic, and a real rush hour can differ. Without traffic: free-flow estimate from OpenStreetMap roads (no traffic).
Chosen from public records by position, not ranked. Nobody can pay to appear here.
Filed documents and where each fact comes from
Filed by the builder on TG-RERA. Each link opens the copy held by the regulator, which may be slow or a scanned page. PropMap.ai links to these papers; it has not checked what they say.
RERA P02200001788 · by Mypi Villas Constructions Phase 2 · SY NO 53P NH44, OPP GVK EMRI, Gundlapochampally, Medchal, 501401
Built by rule from this project's TG-RERA record, read by PropMap.ai on 14/11/2026. Figures are as the builder declared them. The marks and notes are the buyer's own.
Your marks stay on this device. What you mark, the date and your note are not sent to PropMap.ai or to anyone else, and they are lost if this browser's data is cleared. PropMap.ai counts that a mark was made on this project, never what it says. PropMap.ai arranges no visit and sends nothing to the builder.
13 items, none marked yet.
Ask the builder for
RegistrationRegistration ended on 01/06/2025
Ask for: the paper that extends the registration beyond that date, or the paper that certifies the project as complete.Question: “The registration has ended. Which paper extends it or closes it, and may I see it?” See the registration dates
Asked SeenDate: Note:
CompletionThe declared completion date (01/06/2025) has passed
Ask for: the new completion date in writing and, if it exists, the paper that allows people to move in.Question: “What is the new completion date, and has permission to occupy been given for my block?” See declared progress
Asked SeenDate: Note:
An approval paper is filed on TG-RERA; its number is not stated
Ask for: the approval number, and the approved plan that carries it.Question: “What is the approval number, and does the plan show my tower and my floor?” See approvals
Asked SeenDate: Note:
On recordThe builder declared 0 of 103 homes booked (record last updated 28/02/2020)
Ask for: the list of unsold homes of the type you want, with floor and facing.Question: “Which homes of my type are unsold today?” See the booked count
Asked SeenDate: Note:
Filed sizes (3,942 to 3,942 sq ft) are saleable area, not carpet area
Ask for: the carpet area of the flat offered, in writing, and the same figure in the agreement.Question: “What is the carpet area of this flat, and which figure will the agreement carry?” See the filed sizes
Asked SeenDate: Note:
PropMap.ai holds no prices
Ask for: the all-in cost in writing: the price, every other charge, taxes and registration costs, line by line.Question: “What is the total I will pay for this flat, with every charge and tax listed?”
Asked SeenDate: Note:
2 title files are uploaded to TG-RERA; PropMap.ai has not read them
Ask for: copies of the title papers for the land, for your lawyer to read. PropMap.ai does not check title: no flag found is not a clear title.Question: “May my lawyer have copies of the title papers, and of any loan or claim on the land?” See the filed title papers
Asked SeenDate: Note:
Look at on site (6)
On recordRERA number on record: P02200001788
Look at: the registration number printed on the site board, the brochure and any receipt.Question: “Is P02200001788 the number on everything you give me?”
Asked SeenDate: Note:
ConstructionThe filing shows 1 building, the tallest with 5 floors of homes
Look at: how many buildings stand, and the floor the structure has reached in yours. Take dated photos.Question: “Which floor has the structure reached in my tower?” See the filed buildings
Asked SeenDate: Note:
ConstructionThe builder declared 16% of work (record last updated 28/02/2020)
Look at: whether what stands looks like that share of the work: structure, outside finish, lifts and fittings.Question: “What work is going on this month, and what is left before handover?” See declared progress
Asked SeenDate: Note:
The filing lists 13 common facilities
Look at: which of them exist today, such as roads, water supply, drains and open space.Question: “Which shared facilities are finished, and when will the rest be?” See the filed facilities
Asked SeenDate: Note:
On recordA registered address is on record
Look at: that the site you are shown is at the registered address, and what stands on each side of it.Question: “Is this the plot in the registration, and what is planned on the land next to it?” See the registered address
Asked SeenDate: Note:
Drive times on this page are estimates, not measured traffic
Look at: the drive to your daily destination, timed by you at the hour you would travel.Question: “Which road do residents take at peak hour?” See the estimates
Asked SeenDate: Note:
Is this home right for you? Four questions, kept on this device
Is this home right for you?
Answer four questions once, and each project says in words which of your needs its record meets. Kept on this device only.
VILLA 1072 slabs filed
VILLA 1082 slabs filed
VILLA 1092 slabs filed
VILLA 1102 slabs filed
VILLA 1112 slabs filed
VILLA 1122 slabs filed
VILLA 1132 slabs filed
VILLA 1142 slabs filed
VILLA 1152 slabs filed
VILLA 1162 slabs filed
VILLA 1172 slabs filed
VILLA 1182 slabs filed
VILLA 1192 slabs filed
VILLA 1202 slabs filed
VILLA 1212 slabs filed
VILLA 1222 slabs filed
VILLA 1232 slabs filed
VILLA 1242 slabs filed
VILLA 1252 slabs filed
VILLA 1262 slabs filed
VILLA 1272 slabs filed
VILLA 1282 slabs filed
VILLA 1292 slabs filed
VILLA 1302 slabs filed
VILLA 1312 slabs filed
VILLA 1322 slabs filed
VILLA 1332 slabs filed
VILLA 1342 slabs filed
VILLA 1352 slabs filed
VILLA 1362 slabs filed
VILLA 1372 slabs filed
VILLA 1382 slabs filed
VILLA 1392 slabs filed
VILLA 1402 slabs filed
VILLA 1412 slabs filed
VILLA 1422 slabs filed
VILLA 1432 slabs filed
VILLA 1442 slabs filed
VILLA 1452 slabs filed
VILLA 1462 slabs filed
VILLA 1472 slabs filed
VILLA 147A2 slabs filed
VILLA 1482 slabs filed
AMENITIES BLOCK3 slabs filed
The site: land, built-up area, survey number
Land
5.47 acres
Approved built-up area
1,64,673 sq ft
Buildings on the approved plan
51
Towers with homes
1
Highest floor with homes
5 floors
Lost to road widening or a lake's full tank level
None filed
Survey number
SYNO 53P
Site boundaries
east
NEIGHBOURS LAND
west
NEIGHBOURS LAND
north
NEIGHBOURS LAND
south
MYPI VILLAS CONSTRUCTIONS AND APPROACH ROAD
Filed with TG-RERA. People's names are withheld.
Common facilities filed with TG-RERA (14)
Internal Roads & Footpaths0% declared
Water Supply0% declared
Sewerage (Chamber, Lines, Septic Tank , STP)0% declared
Storm Water Drains0% declared
Green Strip/TOT LOT/Park0% declared
Street Lighting0% declared
Community Buildings0% declared
Treatment And Disposal Of Sewage And Sullage Water0% declared
Solid Waste Management And Disposal0% declared
Water Conservation, Rain water Harvesting0% declared
Energy management0% declared
Fire Protection And Fire Safety RequirementsNot provided
Electrical Meter Room, Sub-Station, Receiving Station0% declared
Aggregate area of recreational Open Space0% declared
Labels: Filed with TG-RERA (the builder's filing or the regulator's record), Builder's site says, Measured from open map data, Conflict, Not known. A filing and the builder's own site agreeing does not prove a figure: both come from the builder.
Project location Exact location
Places around this project are not counted yet: locusPro, the location record PropMap.ai uses, covers West Hyderabad only so far. The map shows the project's position only.