Status, as filed
90%work declared by the builder
Filed update 14/10/2025 · read 14/11/2026 · See filing >
What the record shows
Registration ended. TG-RERA record read on 14/11/2026.
Findings from the TG-RERA record
Worked out by PropMap.ai's rules from the dates and figures filed, read 14/11/2026.
Registration. The registration was valid until 09/11/2025 (1 year ago); TG-RERA listed no extension certificate when PropMap.ai read this project on 14/11/2026, and the project status there still reads "New Project". The builder's last filed figure is 90% of work done, in a record last updated 14/10/2025. PropMap.ai cannot tell whether the project is finished and the record was not updated, or work is unfinished. Ask for: the occupancy certificate, or the extension order.
Pictures and plans
4 held
All 4 pictures and plans
Pictures and plans 4
From the builder's website. Pictures may be artist's impressions.
Source: Telangana Real Estate Regulatory Authority (TG-RERA), rera.telangana.gov.in. Reproduced as published; fetched 14/11/2026. The records compared above were read from 14/11/2026 to 24/11/2026. PropMap.ai reports what public records say. It is not legal advice.
Worked out by PropMap.ai from the declared work, the dates and the last-updated date on this page. It does not say the work is delayed.
Orders and complaints are not shown on this page. TG-RERA orders that name this project appear only in its Background Check report, after a compliance review, with the sources searched and their dates.
Madinaguda, Seriingampally, Serilingampally, 500049Filed with TG-RERA
Mandal, district
Serilingampally, Ranga ReddyFiled with TG-RERA
Map position
Approximate: placed from the registered address
Drive times, places nearby and other projects within 5 km
Drive times
Approximate position: placed from the registered address, not the site itself. In our check 4 in 5 such positions were within about 2.5 km, and a few were over 5 km off.
Miyapur≈ 10 min at peak4 min without traffic
Lingampally≈ 17 min at peak7 min without traffic
Kondapur≈ 18 min at peak6 min without traffic
All 42 places
Kukatpally≈ 21 min at peak10 min without traffic
HITEC City≈ 23 min at peak
Documents
Documents uploaded
33 of 38 document slotsFiled with TG-RERA
Document groups on the record
4 (9 documents)Filed with TG-RERA
Pictures and plans held
4
Task-by-task progress, dated certificates and changes between reads
Declared progress as declared by the builder to TG-RERA, not inspected
90%Overall Percentage of Completion of the work done For the entire Building /Wing. Record last updated 14/10/2025; read from TG-RERA on 14/11/2026.No change since the read of 06/11/2026 in the registration dates, completion date or declared work. Of 520 other projects registered in 2021 with a declared work figure, 44 declare more, 441 less and 35 the same, as last filed (records last updated 12/12/2019 to 13/11/2026).
Source: TG-RERA project record, construction table (Tasks / Activity), a web record, not a signed certificate. Dates: the date PropMap.ai read the record; the table gives no as-of date. Percentage of work, as declared by the builder; the total it is measured against is not stated. Covers: whole project (one table filed).
Task-by-task progress (10 tasks)
Excavation100%
Stilt Floor0%
X number of Podiums100%
X number of Basement(s) and Plinth100%
X number of Slabs of Super Structure100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
This filing's proposed completion date is 09/11/2025: of 4 other filings under the same TG-RERA promoter record, 2 have a later date, 2 an earlier one and 0 the same, as last filed (records last updated 03/12/2021 to 12/10/2026).
Not counted on this page, so this is not a count of zero. TG-RERA orders that name a project appear only in that project's Background Check report, after a compliance review.
A passed date does not mean a project is late or unfinished: the filings rarely record completion.
Declared by the builder to TG-RERA, not checked against those projects.
Homes
Homes, total
Left blank in the filing
Booked, as declared
Left blank in the filing
Home types and sizes
Not present in the filing
Types, sizes, bookings and the cost calculator
The counts in this filing did not look believable, so PropMap.ai does not show them. Ask the builder for the numbers in writing.
No price on record. PropMap.ai does not estimate prices. Type the builder's quote
What you type is kept on this device only and is not sent to PropMap.ai. PropMap.ai holds no price of its own: each figure below is an estimate from your quote and from the tax and duty rates listed with their sources.
DLF Cyber City, Gachibowli≈ 25 min at peak9 min without traffic
Balanagar≈ 25 min at peak12 min without traffic
Patancheru≈ 26 min at peak12 min without traffic
Moosapet≈ 27 min at peak12 min without traffic
Gachibowli≈ 27 min at peak10 min without traffic
Raidurg (Mindspace)≈ 27 min at peak9 min without traffic
Khajaguda≈ 30 min at peak12 min without traffic
Financial District≈ 31 min at peak12 min without traffic
Madhapur≈ 31 min at peak11 min without traffic
Jubilee Hills≈ 36 min at peak12 min without traffic
Narsingi≈ 37 min at peak15 min without traffic
Nanakramguda (Waverock)≈ 37 min at peak15 min without traffic
Ameerpet≈ 39 min at peak18 min without traffic
Kokapet≈ 39 min at peak15 min without traffic
Panjagutta≈ 39 min at peak17 min without traffic
Manikonda≈ 40 min at peak15 min without traffic
Lakdikapul≈ 46 min at peak20 min without traffic
Begumpet≈ 47 min at peak20 min without traffic
Banjara Hills≈ 48 min at peak16 min without traffic
Tellapur≈ 50 min at peak20 min without traffic
Mehdipatnam≈ 51 min at peak18 min without traffic
Nampally station (Hyderabad Deccan)≈ 52 min at peak22 min without traffic
Shamshabad≈ 52 min at peak26 min without traffic
Kollur≈ 52 min at peak21 min without traffic
Abids≈ 53 min at peak23 min without traffic
Jeedimetla≈ 54 min at peak23 min without traffic
Koti≈ 56 min at peak24 min without traffic
Secunderabad Junction≈ 58 min at peak23 min without traffic
Kacheguda station≈ 62 min at peak25 min without traffic
Kompally≈ 63 min at peak26 min without traffic
Dilsukhnagar≈ 68 min at peak29 min without traffic
Shamirpet (Genome Valley area)≈ 69 min at peak33 min without traffic
Rajiv Gandhi International Airport≈ 70 min at peak31 min without traffic
LB Nagar≈ 77 min at peak33 min without traffic
Uppal≈ 77 min at peak31 min without traffic
Adibatla (Aerospace SEZ area)≈ 85 min at peak44 min without traffic
Pocharam (Infosys campus area)≈ 98 min at peak44 min without traffic
How these are estimated
Peak: peak estimate: road-type speeds calibrated to TomTom Traffic Index 2025 for Hyderabad (about 15 km/h in the city); not live traffic, and a real rush hour can differ. Without traffic: free-flow estimate from OpenStreetMap roads (no traffic).
Chosen from public records by position, not ranked. Nobody can pay to appear here.
Filed documents and where each fact comes from
Filed by the builder on TG-RERA. Each link opens the copy held by the regulator, which may be slow or a scanned page. PropMap.ai links to these papers; it has not checked what they say.
RERA P02400003777 · by MY Home Constructions PVT. Ltd. · Madinaguda, Seriingampally, Serilingampally, 500049
Built by rule from this project's TG-RERA record, read by PropMap.ai on 14/11/2026. Figures are as the builder declared them. The marks and notes are the buyer's own.
Your marks stay on this device. What you mark, the date and your note are not sent to PropMap.ai or to anyone else, and they are lost if this browser's data is cleared. PropMap.ai counts that a mark was made on this project, never what it says. PropMap.ai arranges no visit and sends nothing to the builder.
10 items, none marked yet.
Ask the builder for
RegistrationRegistration ended on 09/11/2025
Ask for: the paper that extends the registration beyond that date, or the paper that certifies the project as complete.Question: “The registration has ended. Which paper extends it or closes it, and may I see it?” See the registration dates
Asked SeenDate: Note:
CompletionThe declared completion date (09/11/2025) has passed
Ask for: the new completion date in writing and, if it exists, the paper that allows people to move in.Question: “What is the new completion date, and has permission to occupy been given for my block?” See declared progress
Asked SeenDate: Note:
On recordApproval number 1/C21/10154/2021 is declared to TG-RERA
Ask for: the approved plan that carries this number, showing your tower and floor.Question: “Does the approved plan with this number show my tower, my floor and the flat as offered?” See approvals
Asked SeenDate: Note:
PropMap.ai holds no prices
Ask for: the all-in cost in writing: the price, every other charge, taxes and registration costs, line by line.Question: “What is the total I will pay for this flat, with every charge and tax listed?”
Asked SeenDate: Note:
2 title files are uploaded to TG-RERA; PropMap.ai has not read them
Ask for: copies of the title papers for the land, for your lawyer to read. PropMap.ai does not check title: no flag found is not a clear title.Question: “May my lawyer have copies of the title papers, and of any loan or claim on the land?” See the filed title papers
Asked SeenDate: Note:
Look at on site (5)
On recordRERA number on record: P02400003777
Look at: the registration number printed on the site board, the brochure and any receipt.Question: “Is P02400003777 the number on everything you give me?”
Asked SeenDate: Note:
ConstructionThe builder declared 90% of work (record last updated 14/10/2025)
Look at: whether what stands looks like that share of the work: structure, outside finish, lifts and fittings.Question: “What work is going on this month, and what is left before handover?” See declared progress
Asked SeenDate: Note:
The filing lists 15 common facilities
Look at: which of them exist today, such as roads, water supply, drains and open space.Question: “Which shared facilities are finished, and when will the rest be?” See the filed facilities
Asked SeenDate: Note:
PropMap.ai's map position for this project is approximate
Look at: the exact entrance, and what stands on each side of the site.Question: “Is this the plot in the registration, and what is planned on the land next to it?” See the location
Asked SeenDate: Note:
Drive times on this page are estimates, not measured traffic
Look at: the drive to your daily destination, timed by you at the hour you would travel.Question: “Which road do residents take at peak hour?” See the estimates
Asked SeenDate: Note:
Is this home right for you? Four questions, kept on this device
Is this home right for you?
Answer four questions once, and each project says in words which of your needs its record meets. Kept on this device only.
Approximate position: placed from the registered address, not the site itself. In our check 4 in 5 such positions were within about 2.5 km, and a few were over 5 km off.
Labels: Filed with TG-RERA (the builder's filing or the regulator's record), Builder's site says, Measured from open map data, Conflict, Not known. A filing and the builder's own site agreeing does not prove a figure: both come from the builder.
Project location Approximate location
This project's position is approximate: it was placed from the registered address and may be over 2 km from the site. Distances here are measured from that position, so treat them as approximate too.
Approximate position: may be over 2 km off, so distances are approximate too.