Source: Telangana Real Estate Regulatory Authority (TG-RERA), rera.telangana.gov.in. Reproduced as published; fetched 14/11/2026. The records compared above were read from 14/11/2026 to 24/11/2026. PropMap.ai reports what public records say. It is not legal advice.
Name withheld (map ID P02400000820)
Registration. The registration was valid until 09/12/2023, a date that has passed. TG-RERA listed no extension certificate when PropMap.ai read this project on 14/11/2026. Ask for: the extension order, or the occupancy certificate if the project is finished.
Worked out by PropMap.ai from the dates on this page.
Completion. The completion date the builder first filed, 06/11/2024, has passed, and the project status on TG-RERA still reads "New Project" (read 14/11/2026). Ask for: the occupancy certificate, or the revised completion date.
Worked out by PropMap.ai from the dates on this page.
Orders and complaints are not shown on this page. TG-RERA orders that name this project appear only in its Background Check report, after a compliance review, with the sources searched and their dates.
Declared progress
Left blank in the filing
Last updated on TG-RERA
24/07/2025Filed with TG-RERA
Actual completion
Not present in the filing
Occupancy certificate
Not present in the filing
Task-by-task progress, dated certificates and changes between reads
Declared progress as declared by the builder to TG-RERA, not inspected
No overall figure filed for the project. The record files 5 building tables and no project figure; each is shown as filed, in the record's order, and none is averaged. Read from TG-RERA on 14/11/2026.
Not counted on this page, so this is not a count of zero. TG-RERA orders that name a project appear only in that project's Background Check report, after a compliance review.
A passed date does not mean a project is late or unfinished: the filings rarely record completion.
As declared to TG-RERA. The filing gives counts, not which flat is free, so confirm any flat with the builder. Of 352 other projects in Gandipet mandal with a booked count, 92 declare a larger share booked, 260 a smaller one and 0 the same, as last filed (records last updated 12/12/2018 to 23/11/2026).
Home types
Type
Homes
Not booked
Saleable size
2 BHK
131
72
1,184 to 1,775 sq ft
3 BHK
235
175
1,381 to 2,810 sq ft
Saleable area, not carpet area. Ask for the carpet area in writing. 1 other unit is filed without a bedroom type, such as clubhouses or shops.
No price on record. PropMap.ai does not estimate prices. Type the builder's quote
What you type is kept on this device only and is not sent to PropMap.ai. PropMap.ai holds no price of its own: each figure below is an estimate from your quote and from the tax and duty rates listed with their sources.
Location
Registered address
PUPPALGUDA, GANDIPET, 500034Filed with TG-RERA
Mandal, district
Gandipet, Ranga ReddyFiled with TG-RERA
Map position
Approximate: placed from the registered address
Drive times, places nearby and other projects within 5 km
Drive times
Approximate position: placed from the registered address, not the site itself. In our check 4 in 5 such positions were within about 2.5 km, and a few were over 5 km off.
Raidurg (Mindspace)≈ 15 min at peak7 min without traffic
Khajaguda≈ 15 min at peak6 min without traffic
Gachibowli≈ 15 min at peak7 min without traffic
All 42 places
DLF Cyber City, Gachibowli≈ 15 min at peak7 min without traffic
Financial District≈ 17 min at peak
Documents
Documents uploaded
24 of 31 document slotsFiled with TG-RERA
Document groups on the record
3 (7 documents)Filed with TG-RERA
Pictures and plans held
7
Source: TG-RERA project record, construction table (Tasks / Activity), a web record, not a signed certificate. Dates: the date PropMap.ai read the record; the table gives no as-of date. Percentage of work, as declared by the builder; the total it is measured against is not stated. Covers: 5 building tables, no project figure filed.
No change between PropMap.ai's reads of 06/11/2026 and 14/11/2026 in the registration dates, completion date or declared work (68.4%).
Earlier projects the builder declared (8)
Project
Homes
Promised
Finished
BLOOM DALE
1
06/02/2015
06/02/2015
YELLOW STONE
1
26/05/2018
26/05/2018
PURPLE TUNES
1
26/05/2018
26/05/2018
99 PARK
1
01/10/2016
01/10/2016
ORANGE SPRINGS
1
13/08/2014
13/08/2014
TIMBRE
1
01/10/2016
01/10/2016
MEDA HEIGHTS
1
31/01/2018
31/01/2018
MORNING RAGA
1
08/08/2018
08/08/2018
Declared by the builder to TG-RERA, not checked against those projects.
Towers, floor by floor (5)
booked not booked, as declared.
RAMI REDDY- BLOCK A10 floors with homes · 10 slabs filed · 1 basement · 120 homes, 56 booked
102 of 12
98 of 12
86 of 12
76 of 12
67 of 12
59 of 12
47 of 12
37 of 12
24 of 12
10 of 12
RAMI REDDY-BLOCK B10 floors with homes · 10 slabs filed · 1 basement · 115 homes, 24 booked
103 of 12
91 of 12
85 of 12
72 of 12
66 of 12
5
RAMI REDDY-BLOCK C10 floors with homes · 10 slabs filed · 1 basement · 80 homes, 39 booked
100 of 8
95 of 8
83 of 8
77 of 8
66 of 8
5
RAMI REDDY-BLOCK D10 floors with homes · 10 slabs filed · 1 basement · 51 homes, 0 booked
100 of 5
90 of 5
80 of 6
70 of 5
60 of 5
50 of 5
40 of 5
30 of 5
2
CLUB HOUSE4 slabs filed · 1 basement
The site: land, built-up area, survey number
Land
4.33 acres
Net of road and water setbacks
4.07 acres
Approved built-up area
6,97,406 sq ft
Buildings on the approved plan
5
Towers with homes
4
Highest floor with homes
10 floors
Lost to road widening or a lake's full tank level
11,156 sq ft
Survey number
176 232 233 AND 234 SECTOR III BLOCK C
Site boundaries
east
ROAD WIDTH 30
west
CTS NO
north
ROAD WIDTH 30
south
ROAD WIDTH 30
Filed with TG-RERA. People's names are withheld.
Common facilities filed with TG-RERA (14)
Internal Roads & Footpaths80% declared
Water Supply60% declared
Sewerage (Chamber, Lines, Septic Tank , STP)80% declared
Storm Water Drains70% declared
Green Strip/TOT LOT/Park20% declared
Street Lighting80% declared
Community Buildings80% declared
Treatment And Disposal Of Sewage And Sullage WaterNot provided
Solid Waste Management And DisposalNot provided
Water Conservation, Rain water Harvesting80% declared
Energy managementNot provided
Fire Protection And Fire Safety Requirements60% declared
Electrical Meter Room, Sub-Station, Receiving Station60% declared
Aggregate area of recreational Open SpaceNot provided
Declared by the builder, not inspected.
Amenities (5)
gym
landscaped garden
power backup
security
swimming pool
Builder's site says · anuhar.com ↗ · read 13/11/2026
8 min without traffic
Nanakramguda (Waverock)≈ 17 min at peak8 min without traffic
Kondapur≈ 18 min at peak8 min without traffic
HITEC City≈ 19 min at peak9 min without traffic
Narsingi≈ 23 min at peak10 min without traffic
Kokapet≈ 25 min at peak11 min without traffic
Manikonda≈ 25 min at peak10 min without traffic
Madhapur≈ 26 min at peak11 min without traffic
Jubilee Hills≈ 32 min at peak13 min without traffic
Miyapur≈ 34 min at peak14 min without traffic
Tellapur≈ 36 min at peak17 min without traffic
Lingampally≈ 36 min at peak15 min without traffic
Mehdipatnam≈ 38 min at peak14 min without traffic
Shamshabad≈ 38 min at peak21 min without traffic
Kollur≈ 38 min at peak18 min without traffic
Kukatpally≈ 39 min at peak16 min without traffic
Banjara Hills≈ 43 min at peak16 min without traffic
Balanagar≈ 43 min at peak18 min without traffic
Moosapet≈ 45 min at peak18 min without traffic
Panjagutta≈ 45 min at peak17 min without traffic
Patancheru≈ 45 min at peak22 min without traffic
Lakdikapul≈ 47 min at peak18 min without traffic
Ameerpet≈ 49 min at peak18 min without traffic
Nampally station (Hyderabad Deccan)≈ 53 min at peak20 min without traffic
Begumpet≈ 54 min at peak20 min without traffic
Abids≈ 54 min at peak21 min without traffic
Rajiv Gandhi International Airport≈ 56 min at peak27 min without traffic
Koti≈ 57 min at peak22 min without traffic
Kacheguda station≈ 63 min at peak24 min without traffic
Secunderabad Junction≈ 63 min at peak24 min without traffic
Dilsukhnagar≈ 69 min at peak27 min without traffic
Adibatla (Aerospace SEZ area)≈ 71 min at peak39 min without traffic
Jeedimetla≈ 72 min at peak29 min without traffic
LB Nagar≈ 78 min at peak32 min without traffic
Uppal≈ 78 min at peak31 min without traffic
Kompally≈ 81 min at peak32 min without traffic
Shamirpet (Genome Valley area)≈ 84 min at peak42 min without traffic
Pocharam (Infosys campus area)≈ 101 min at peak43 min without traffic
How these are estimated
Peak: peak estimate: road-type speeds calibrated to TomTom Traffic Index 2025 for Hyderabad (about 15 km/h in the city); not live traffic, and a real rush hour can differ. Without traffic: free-flow estimate from OpenStreetMap roads (no traffic).
Chosen from public records by position, not ranked. Nobody can pay to appear here.
Filed documents and where each fact comes from
Filed by the builder on TG-RERA. Each link opens the copy held by the regulator, which may be slow or a scanned page. PropMap.ai links to these papers; it has not checked what they say.
Site-visit sheet: Name withheld (map ID P02400000820)
RERA P02400000820 · by Anuhar Homes Private Limited · PUPPALGUDA, GANDIPET, 500034
Built by rule from this project's TG-RERA record, read by PropMap.ai on 14/11/2026. Figures are as the builder declared them. The marks and notes are the buyer's own.
Your marks stay on this device. What you mark, the date and your note are not sent to PropMap.ai or to anyone else, and they are lost if this browser's data is cleared. PropMap.ai counts that a mark was made on this project, never what it says. PropMap.ai arranges no visit and sends nothing to the builder.
12 items, none marked yet.
Ask the builder for
RegistrationRegistration ended on 09/12/2023
Ask for: the paper that extends the registration beyond that date, or the paper that certifies the project as complete.Question: “The registration has ended. Which paper extends it or closes it, and may I see it?” See the registration dates
Asked SeenDate: Note:
CompletionThe declared completion date (06/11/2024) has passed
Ask for: the new completion date in writing and, if it exists, the paper that allows people to move in.Question: “What is the new completion date, and has permission to occupy been given for my block?” See declared progress
Asked SeenDate: Note:
On recordThe builder declared 119 of 367 homes booked (record last updated 24/07/2025)
Ask for: the list of unsold homes of the type you want, with floor and facing.Question: “Which homes of my type are unsold today?” See the booked count
Asked SeenDate: Note:
Filed sizes (1,184 to 2,810 sq ft) are saleable area, not carpet area
Ask for: the carpet area of the flat offered, in writing, and the same figure in the agreement.Question: “What is the carpet area of this flat, and which figure will the agreement carry?” See the filed sizes
Asked SeenDate: Note:
PropMap.ai holds no prices
Ask for: the all-in cost in writing: the price, every other charge, taxes and registration costs, line by line.Question: “What is the total I will pay for this flat, with every charge and tax listed?”
Asked SeenDate: Note:
1 title file is uploaded to TG-RERA; PropMap.ai has not read them
Ask for: copies of the title papers for the land, for your lawyer to read. PropMap.ai does not check title: no flag found is not a clear title.Question: “May my lawyer have copies of the title papers, and of any loan or claim on the land?” See the filed title papers
Asked SeenDate: Note:
Look at on site (6)
On recordRERA number on record: P02400000820
Look at: the registration number printed on the site board, the brochure and any receipt.Question: “Is P02400000820 the number on everything you give me?”
Asked SeenDate: Note:
ConstructionThe filing shows 4 buildings, the tallest with 10 floors of homes
Look at: how many buildings stand, and the floor the structure has reached in yours. Take dated photos.Question: “Which floor has the structure reached in my tower?” See the filed buildings
Asked SeenDate: Note:
ConstructionThe builder declared 68% of work (record last updated 24/07/2025)
Look at: whether what stands looks like that share of the work: structure, outside finish, lifts and fittings.Question: “What work is going on this month, and what is left before handover?” See declared progress
Asked SeenDate: Note:
The filing lists 10 common facilities
Look at: which of them exist today, such as roads, water supply, drains and open space.Question: “Which shared facilities are finished, and when will the rest be?” See the filed facilities
Asked SeenDate: Note:
PropMap.ai's map position for this project is approximate
Look at: the exact entrance, and what stands on each side of the site.Question: “Is this the plot in the registration, and what is planned on the land next to it?” See the location
Asked SeenDate: Note:
Drive times on this page are estimates, not measured traffic
Look at: the drive to your daily destination, timed by you at the hour you would travel.Question: “Which road do residents take at peak hour?” See the estimates
Asked SeenDate: Note:
Is this home right for you? Four questions, kept on this device
Is this home right for you?
Answer four questions once, and each project says in words which of your needs its record meets. Kept on this device only.
Approximate position: placed from the registered address, not the site itself. In our check 4 in 5 such positions were within about 2.5 km, and a few were over 5 km off.
Labels: Filed with TG-RERA (the builder's filing or the regulator's record), Builder's site says, Measured from open map data, Conflict, Not known. A filing and the builder's own site agreeing does not prove a figure: both come from the builder.
Project location Approximate location
This project's position is approximate: it was placed from the registered address and may be over 2 km from the site. Distances here are measured from that position, so treat them as approximate too.
Approximate position: may be over 2 km off, so distances are approximate too.
Listed nearby within 2 km