Filed update 10/11/2023 · read 14/11/2026 · See filing >
What the record shows
Registration ended. TG-RERA record read on 14/11/2026.
Findings from the TG-RERA record
Worked out by PropMap.ai's rules from the dates and figures filed, read 14/11/2026.
Registration. The registration was valid until 21/06/2024 (2 years and 5 months ago); TG-RERA listed no extension certificate when PropMap.ai read this project on 14/11/2026, and the project status there still reads "New Project". The builder's last filed figure is 36% of work done, in a record last updated 10/11/2023. PropMap.ai cannot tell whether the project is finished and the record was not updated, or work is unfinished. Ask for: the occupancy certificate, or the extension order.
Source: Telangana Real Estate Regulatory Authority (TG-RERA), rera.telangana.gov.in. Reproduced as published; fetched 14/11/2026. The records compared above were read from 14/11/2026 to 24/11/2026. PropMap.ai reports what public records say. It is not legal advice.
Worked out by PropMap.ai from the declared work, the dates and the last-updated date on this page. It does not say the work is delayed.
Orders and complaints are not shown on this page. TG-RERA orders that name this project appear only in its Background Check report, after a compliance review, with the sources searched and their dates.
RAGHAVENDRA COLONY, Serilingampally, 500084Filed with TG-RERA
Mandal, district
Serilingampally, Ranga ReddyFiled with TG-RERA
Map position
Exact: the TG-RERA portal's map pinFiled with TG-RERA
Drive times, places nearby and other projects within 5 km
Drive times
Kondapur≈ 11 min at peak4 min without traffic
HITEC City≈ 15 min at peak6 min without traffic
Miyapur≈ 16 min at peak6 min without traffic
All 42 places
DLF Cyber City, Gachibowli≈ 17 min at peak6 min without traffic
Raidurg (Mindspace)≈ 20 min at peak7 min without traffic
Documents
Documents uploaded
29 of 36 document slotsFiled with TG-RERA
Document groups on the record
3 (8 documents)Filed with TG-RERA
Pictures and plans held
0
Task-by-task progress, dated certificates and changes between reads
Declared progress as declared by the builder to TG-RERA, not inspected
36%Overall Percentage of Completion of the work done For the entire Building /Wing. Record last updated 10/11/2023; read from TG-RERA on 14/11/2026.No change since the read of 04/11/2026 in the registration dates, completion date or declared work. Of 549 other projects registered in 2019 with a declared work figure, 326 declare more, 219 less and 4 the same, as last filed (records last updated 29/11/2018 to 23/10/2026).
Source: TG-RERA project record, construction table (Tasks / Activity), a web record, not a signed certificate. Dates: the date PropMap.ai read the record; the table gives no as-of date. Percentage of work, as declared by the builder; the total it is measured against is not stated. Covers: whole project (one table filed).
Not counted on this page, so this is not a count of zero. TG-RERA orders that name a project appear only in that project's Background Check report, after a compliance review.
A passed date does not mean a project is late or unfinished: the filings rarely record completion.
As declared to TG-RERA. The filing gives counts, not which flat is free, so confirm any flat with the builder. Of 420 other projects in Serilingampally mandal with a booked count, 108 declare a larger share booked, 312 a smaller one and 0 the same, as last filed (records last updated 12/12/2018 to 13/11/2026).
Home types
Type
Homes
Not booked
Saleable size
3 BHK
3,015
1,910
1,292 sq ft
Saleable area, not carpet area. Ask for the carpet area in writing.
No price on record. PropMap.ai does not estimate prices. Type the builder's quote
What you type is kept on this device only and is not sent to PropMap.ai. PropMap.ai holds no price of its own: each figure below is an estimate from your quote and from the tax and duty rates listed with their sources.
Towers, floor by floor (1)
booked not booked, as declared.
KHYATHI NILAYAM5 floors with homes · 6 slabs filed · 3,015 homes, 1,105 booked
50 of 1003
4
Gachibowli
≈ 20 min at peak
7 min without traffic
Khajaguda≈ 22 min at peak9 min without traffic
Financial District≈ 23 min at peak10 min without traffic
Madhapur≈ 23 min at peak8 min without traffic
Lingampally≈ 24 min at peak10 min without traffic
Kukatpally≈ 27 min at peak10 min without traffic
Jubilee Hills≈ 28 min at peak10 min without traffic
Narsingi≈ 29 min at peak12 min without traffic
Nanakramguda (Waverock)≈ 30 min at peak13 min without traffic
Kokapet≈ 32 min at peak13 min without traffic
Balanagar≈ 32 min at peak13 min without traffic
Manikonda≈ 32 min at peak13 min without traffic
Moosapet≈ 33 min at peak13 min without traffic
Patancheru≈ 34 min at peak15 min without traffic
Banjara Hills≈ 40 min at peak14 min without traffic
Panjagutta≈ 42 min at peak14 min without traffic
Tellapur≈ 43 min at peak21 min without traffic
Mehdipatnam≈ 43 min at peak15 min without traffic
Shamshabad≈ 44 min at peak23 min without traffic
Ameerpet≈ 45 min at peak16 min without traffic
Kollur≈ 45 min at peak22 min without traffic
Lakdikapul≈ 48 min at peak17 min without traffic
Begumpet≈ 51 min at peak18 min without traffic
Nampally station (Hyderabad Deccan)≈ 54 min at peak20 min without traffic
Abids≈ 56 min at peak20 min without traffic
Koti≈ 58 min at peak22 min without traffic
Jeedimetla≈ 61 min at peak24 min without traffic
Rajiv Gandhi International Airport≈ 62 min at peak29 min without traffic
Kacheguda station≈ 64 min at peak23 min without traffic
Secunderabad Junction≈ 64 min at peak22 min without traffic
Kompally≈ 70 min at peak27 min without traffic
Dilsukhnagar≈ 70 min at peak27 min without traffic
Shamirpet (Genome Valley area)≈ 76 min at peak35 min without traffic
Adibatla (Aerospace SEZ area)≈ 77 min at peak42 min without traffic
LB Nagar≈ 79 min at peak31 min without traffic
Uppal≈ 80 min at peak29 min without traffic
Pocharam (Infosys campus area)≈ 104 min at peak42 min without traffic
How these are estimated
Peak: peak estimate: road-type speeds calibrated to TomTom Traffic Index 2025 for Hyderabad (about 15 km/h in the city); not live traffic, and a real rush hour can differ. Without traffic: free-flow estimate from OpenStreetMap roads (no traffic).
Chosen from public records by position, not ranked. Nobody can pay to appear here.
Filed documents and where each fact comes from
Filed by the builder on TG-RERA. Each link opens the copy held by the regulator, which may be slow or a scanned page. PropMap.ai links to these papers; it has not checked what they say.
Built by rule from this project's TG-RERA record, read by PropMap.ai on 14/11/2026. Figures are as the builder declared them. The marks and notes are the buyer's own.
Your marks stay on this device. What you mark, the date and your note are not sent to PropMap.ai or to anyone else, and they are lost if this browser's data is cleared. PropMap.ai counts that a mark was made on this project, never what it says. PropMap.ai arranges no visit and sends nothing to the builder.
14 items, none marked yet.
Ask the builder for
RegistrationRegistration ended on 21/06/2024
Ask for: the paper that extends the registration beyond that date, or the paper that certifies the project as complete.Question: “The registration has ended. Which paper extends it or closes it, and may I see it?” See the registration dates
Asked SeenDate: Note:
CompletionThe declared completion date (21/06/2024) has passed
Ask for: the new completion date in writing and, if it exists, the paper that allows people to move in.Question: “What is the new completion date, and has permission to occupy been given for my block?” See declared progress
Asked SeenDate: Note:
On recordApproval number 2/C20/10485/2018 is declared to TG-RERA
Ask for: the approved plan that carries this number, showing your tower and floor.Question: “Does the approved plan with this number show my tower, my floor and the flat as offered?” See approvals
Asked SeenDate: Note:
On recordAn occupancy certificate dated 30/05/2026 is filed (Verification Pending)
Ask for: the certificate itself, and which blocks and floors it covers.Question: “Does this certificate cover my block and my floor?” See the filed certificate
Asked SeenDate: Note:
On recordThe builder declared 1,105 of 3,015 homes booked (record last updated 10/11/2023)
Ask for: the list of unsold homes of the type you want, with floor and facing.Question: “Which homes of my type are unsold today?” See the booked count
Asked SeenDate: Note:
Filed sizes (1,292 to 1,292 sq ft) are saleable area, not carpet area
Ask for: the carpet area of the flat offered, in writing, and the same figure in the agreement.Question: “What is the carpet area of this flat, and which figure will the agreement carry?” See the filed sizes
Asked SeenDate: Note:
PropMap.ai holds no prices
Ask for: the all-in cost in writing: the price, every other charge, taxes and registration costs, line by line.Question: “What is the total I will pay for this flat, with every charge and tax listed?”
Asked SeenDate: Note:
2 title files are uploaded to TG-RERA; PropMap.ai has not read them
Ask for: copies of the title papers for the land, for your lawyer to read. PropMap.ai does not check title: no flag found is not a clear title.Question: “May my lawyer have copies of the title papers, and of any loan or claim on the land?” See the filed title papers
Asked SeenDate: Note:
Look at on site (6)
On recordRERA number on record: P02400000667
Look at: the registration number printed on the site board, the brochure and any receipt.Question: “Is P02400000667 the number on everything you give me?”
Asked SeenDate: Note:
ConstructionThe filing shows 1 building, the tallest with 5 floors of homes
Look at: how many buildings stand, and the floor the structure has reached in yours. Take dated photos.Question: “Which floor has the structure reached in my tower?” See the filed buildings
Asked SeenDate: Note:
ConstructionThe builder declared 36% of work (record last updated 10/11/2023)
Look at: whether what stands looks like that share of the work: structure, outside finish, lifts and fittings.Question: “What work is going on this month, and what is left before handover?” See declared progress
Asked SeenDate: Note:
The filing lists 4 common facilities
Look at: which of them exist today, such as roads, water supply, drains and open space.Question: “Which shared facilities are finished, and when will the rest be?” See the filed facilities
Asked SeenDate: Note:
On recordA registered address is on record
Look at: that the site you are shown is at the registered address, and what stands on each side of it.Question: “Is this the plot in the registration, and what is planned on the land next to it?” See the registered address
Asked SeenDate: Note:
Drive times on this page are estimates, not measured traffic
Look at: the drive to your daily destination, timed by you at the hour you would travel.Question: “Which road do residents take at peak hour?” See the estimates
Asked SeenDate: Note:
Is this home right for you? Four questions, kept on this device
Is this home right for you?
Answer four questions once, and each project says in words which of your needs its record meets. Kept on this device only.
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises60%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
803 of 803
3302 of 603
20 of 403
10 of 203
The site: land, built-up area, survey number
Land
0.12 acres
Approved built-up area
13,331 sq ft
Buildings on the approved plan
1
Towers with homes
1
Highest floor with homes
5 floors
Lost to road widening or a lake's full tank level
None filed
Survey number
77
Site boundaries
east
18270
west
18270
north
27400
south
27400
Filed with TG-RERA. People's names are withheld.
Common facilities filed with TG-RERA (14)
Internal Roads & FootpathsNot provided
Water Supply0% declared
Sewerage (Chamber, Lines, Septic Tank , STP)0% declared
Storm Water Drains0% declared
Green Strip/TOT LOT/ParkNot provided
Street LightingNot provided
Community BuildingsNot provided
Treatment And Disposal Of Sewage And Sullage WaterNot provided
Solid Waste Management And DisposalNot provided
Water Conservation, Rain water Harvesting0% declared
Energy managementNot provided
Fire Protection And Fire Safety RequirementsNot provided
Electrical Meter Room, Sub-Station, Receiving StationNot provided
Aggregate area of recreational Open SpaceNot provided
Labels: Filed with TG-RERA (the builder's filing or the regulator's record), Builder's site says, Measured from open map data, Conflict, Not known. A filing and the builder's own site agreeing does not prove a figure: both come from the builder.