Left blank in the filingwork declared by the builder, 3 building tables
Building table 190.5%
Building table 287.2%
Building table 382%
Filed update 21/05/2023 · read 14/11/2026 · See filing >
What the record shows
Registration ended. TG-RERA record read on 14/11/2026.
Findings from the TG-RERA record
Worked out by PropMap.ai's rules from the dates and figures filed, read 14/11/2026.
The registration was valid until 01/01/2024, a date that has passed. TG-RERA listed no extension certificate when PropMap.ai read this project on 14/11/2026. Ask for: the extension order, or the occupancy certificate if the project is finished.
Source: Telangana Real Estate Regulatory Authority (TG-RERA), rera.telangana.gov.in. Reproduced as published; fetched 14/11/2026. The records compared above were read from 14/11/2026 to 24/11/2026. PropMap.ai reports what public records say. It is not legal advice.
Sukhii9
Registration.
Worked out by PropMap.ai from the dates on this page.
Completion. The revised completion date the builder filed, 01/01/2024, has passed, and the project status on TG-RERA still reads "On-Going Project" (read 14/11/2026). Ask for: the occupancy certificate, or the revised completion date.
Worked out by PropMap.ai from the dates on this page.
Orders and complaints are not shown on this page. TG-RERA orders that name this project appear only in its Background Check report, after a compliance review, with the sources searched and their dates.
Road No-2, Kousalya Colony, Krishnaja Hills, Bachupally, 500049Filed with TG-RERA
Mandal, district
Bachupally, Medchal-MalkajgiriFiled with TG-RERA
Map position
Exact: the TG-RERA portal's map pinFiled with TG-RERA
Drive times, places nearby and other projects within 5 km
Drive times
Miyapur≈ 15 min at peak6 min without traffic
Kukatpally≈ 22 min at peak9 min without traffic
Balanagar≈ 26 min at peak11 min without traffic
All 42 places
Lingampally≈ 28 min at peak11 min without traffic
Moosapet≈ 28 min at peak12 min without traffic
Documents
Documents uploaded
18 of 28 document slotsFiled with TG-RERA
Document groups on the record
3 (6 documents)Filed with TG-RERA
Pictures and plans held
0
Task-by-task progress, dated certificates and changes between reads
Declared progress as declared by the builder to TG-RERA, not inspected
No overall figure filed for the project. The record files 3 building tables and no project figure; each is shown as filed, in the record's order, and none is averaged. Read from TG-RERA on 14/11/2026.
Building table 190.5%
Building table 287.2%
Building table 382%
Source: TG-RERA project record, construction table (Tasks / Activity), a web record, not a signed certificate. Dates: the date PropMap.ai read the record; the table gives no as-of date. Percentage of work, as declared by the builder; the total it is measured against is not stated. Covers: 3 building tables, no project figure filed.
No change between PropMap.ai's reads of 05/11/2026 and 14/11/2026 in the registration dates, completion date or declared work (86.6%).
Not counted on this page, so this is not a count of zero. TG-RERA orders that name a project appear only in that project's Background Check report, after a compliance review.
A passed date does not mean a project is late or unfinished: the filings rarely record completion.
As declared to TG-RERA. The filing gives counts, not which flat is free, so confirm any flat with the builder. Of 130 other projects in Bachupally mandal with a booked count, 25 declare a larger share booked, 105 a smaller one and 0 the same, as last filed (records last updated 09/01/2019 to 30/10/2026).
239 units filed with TG-RERA without a bedroom type.
No price on record. PropMap.ai does not estimate prices. Type the builder's quote
What you type is kept on this device only and is not sent to PropMap.ai. PropMap.ai holds no price of its own: each figure below is an estimate from your quote and from the tax and duty rates listed with their sources.
DLF Cyber City, Gachibowli≈ 37 min at peak13 min without traffic
Patancheru≈ 37 min at peak16 min without traffic
Raidurg (Mindspace)≈ 39 min at peak14 min without traffic
Gachibowli≈ 39 min at peak14 min without traffic
Ameerpet≈ 40 min at peak17 min without traffic
Panjagutta≈ 40 min at peak18 min without traffic
Khajaguda≈ 42 min at peak16 min without traffic
Financial District≈ 43 min at peak16 min without traffic
Madhapur≈ 43 min at peak15 min without traffic
Lakdikapul≈ 47 min at peak21 min without traffic
Jubilee Hills≈ 47 min at peak17 min without traffic
Begumpet≈ 48 min at peak20 min without traffic
Narsingi≈ 49 min at peak19 min without traffic
Nanakramguda (Waverock)≈ 49 min at peak20 min without traffic
Banjara Hills≈ 50 min at peak21 min without traffic
Tellapur≈ 50 min at peak24 min without traffic
Kokapet≈ 51 min at peak20 min without traffic
Manikonda≈ 51 min at peak19 min without traffic
Shamirpet (Genome Valley area)≈ 53 min at peak27 min without traffic
Nampally station (Hyderabad Deccan)≈ 53 min at peak24 min without traffic
Kompally≈ 53 min at peak23 min without traffic
Kollur≈ 54 min at peak26 min without traffic
Abids≈ 54 min at peak24 min without traffic
Jeedimetla≈ 55 min at peak21 min without traffic
Mehdipatnam≈ 56 min at peak22 min without traffic
Koti≈ 57 min at peak25 min without traffic
Secunderabad Junction≈ 59 min at peak23 min without traffic
Kacheguda station≈ 63 min at peak26 min without traffic
Shamshabad≈ 64 min at peak30 min without traffic
Dilsukhnagar≈ 69 min at peak30 min without traffic
LB Nagar≈ 78 min at peak34 min without traffic
Uppal≈ 78 min at peak30 min without traffic
Pocharam (Infosys campus area)≈ 82 min at peak43 min without traffic
Rajiv Gandhi International Airport≈ 82 min at peak36 min without traffic
Adibatla (Aerospace SEZ area)≈ 97 min at peak48 min without traffic
How these are estimated
Peak: peak estimate: road-type speeds calibrated to TomTom Traffic Index 2025 for Hyderabad (about 15 km/h in the city); not live traffic, and a real rush hour can differ. Without traffic: free-flow estimate from OpenStreetMap roads (no traffic).
Chosen from public records by position, not ranked. Nobody can pay to appear here.
Filed documents and where each fact comes from
Filed by the builder on TG-RERA. Each link opens the copy held by the regulator, which may be slow or a scanned page. PropMap.ai links to these papers; it has not checked what they say.
RERA P02200000037 · by NJR Constructions Private Limited · Road No-2, Kousalya Colony, Krishnaja Hills, Bachupally, 500049
Built by rule from this project's TG-RERA record, read by PropMap.ai on 14/11/2026. Figures are as the builder declared them. The marks and notes are the buyer's own.
Your marks stay on this device. What you mark, the date and your note are not sent to PropMap.ai or to anyone else, and they are lost if this browser's data is cleared. PropMap.ai counts that a mark was made on this project, never what it says. PropMap.ai arranges no visit and sends nothing to the builder.
11 items, none marked yet.
Ask the builder for
RegistrationRegistration ended on 01/01/2024
Ask for: the paper that extends the registration beyond that date, or the paper that certifies the project as complete.Question: “The registration has ended. Which paper extends it or closes it, and may I see it?” See the registration dates
Asked SeenDate: Note:
CompletionThe declared completion date (01/01/2024) has passed
Ask for: the new completion date in writing and, if it exists, the paper that allows people to move in.Question: “What is the new completion date, and has permission to occupy been given for my block?” See declared progress
Asked SeenDate: Note:
On recordApproval number 003075/MED/R1/U6/HMDA/26082017 is declared to TG-RERA
Ask for: the approved plan that carries this number, showing your tower and floor.Question: “Does the approved plan with this number show my tower, my floor and the flat as offered?” See approvals
Asked SeenDate: Note:
On recordThe builder declared 148 of 239 homes booked (record last updated 21/05/2023)
Ask for: the list of unsold homes of the type you want, with floor and facing.Question: “Which homes of my type are unsold today?” See the booked count
Asked SeenDate: Note:
PropMap.ai holds no prices
Ask for: the all-in cost in writing: the price, every other charge, taxes and registration costs, line by line.Question: “What is the total I will pay for this flat, with every charge and tax listed?”
Asked SeenDate: Note:
2 title files are uploaded to TG-RERA; PropMap.ai has not read them
Ask for: copies of the title papers for the land, for your lawyer to read. PropMap.ai does not check title: no flag found is not a clear title.Question: “May my lawyer have copies of the title papers, and of any loan or claim on the land?” See the filed title papers
Asked SeenDate: Note:
Look at on site (5)
On recordRERA number on record: P02200000037
Look at: the registration number printed on the site board, the brochure and any receipt.Question: “Is P02200000037 the number on everything you give me?”
Asked SeenDate: Note:
ConstructionThe filing shows 3 buildings
Look at: how many buildings stand, and the floor the structure has reached in yours. Take dated photos.Question: “Which floor has the structure reached in my tower?” See the filed buildings
Asked SeenDate: Note:
The filing lists 13 common facilities
Look at: which of them exist today, such as roads, water supply, drains and open space.Question: “Which shared facilities are finished, and when will the rest be?” See the filed facilities
Asked SeenDate: Note:
On recordA registered address is on record
Look at: that the site you are shown is at the registered address, and what stands on each side of it.Question: “Is this the plot in the registration, and what is planned on the land next to it?” See the registered address
Asked SeenDate: Note:
Drive times on this page are estimates, not measured traffic
Look at: the drive to your daily destination, timed by you at the hour you would travel.Question: “Which road do residents take at peak hour?” See the estimates
Asked SeenDate: Note:
Is this home right for you? Four questions, kept on this device
Is this home right for you?
Answer four questions once, and each project says in words which of your needs its record meets. Kept on this device only.
Treatment And Disposal Of Sewage And Sullage Water50% declared
Solid Waste Management And DisposalNot provided
Water Conservation, Rain water Harvesting60% declared
Energy management15% declared
Fire Protection And Fire Safety Requirements70% declared
Electrical Meter Room, Sub-Station, Receiving Station50% declared
Aggregate area of recreational Open Space10% declared
Internal Roads & Footpaths10% declared
Water Supply20% declared
Sewerage (Chamber, Lines, Septic Tank , STP)45% declared
Labels: Filed with TG-RERA (the builder's filing or the regulator's record), Builder's site says, Measured from open map data, Conflict, Not known. A filing and the builder's own site agreeing does not prove a figure: both come from the builder.
Project location Exact location
Listed nearby within 2 km
2 km: about 7 to 14 min drive at peak. Nearest first.