Filed update 30/04/2026 · read 14/11/2026 · See filing >
What the record shows
Registered now. As published on TG-RERA. TG-RERA record read on 14/11/2026.
Findings from the TG-RERA record
No finding. PropMap.ai's rules (registration dates, extensions, status, filed work) found nothing to report in this project's TG-RERA record, read 14/11/2026.
Registration status
Registration number
P02200006119Filed with TG-RERA
Registered on
24/04/2023Filed with TG-RERA
Valid until
30/04/2028Filed with TG-RERA
Extensions
At least 1, the latest valid until 30/08/2028Filed with TG-RERA
Source: Telangana Real Estate Regulatory Authority (TG-RERA), rera.telangana.gov.in. Reproduced as published; fetched 14/11/2026. The records compared above were read from 14/11/2026 to 24/11/2026. PropMap.ai reports what public records say. It is not legal advice.
Green Scapes
This covers only those rules and that record. It is not a clear title or a legal all-clear.
Orders and complaints are not shown on this page. TG-RERA orders that name this project appear only in its Background Check report, after a compliance review, with the sources searched and their dates.
Bowrampet, Dundigal Gandimaisamma, 500043Filed with TG-RERA
Mandal, district
Dundigal Gandimaisamma, Medchal-MalkajgiriFiled with TG-RERA
Map position
Approximate: placed from the registered address
Drive times, places nearby and other projects within 5 km
Drive times
Approximate position: placed from the registered address, not the site itself. In our check 4 in 5 such positions were within about 2.5 km, and a few were over 5 km off.
Kukatpally≈ 35 min at peak13 min without traffic
Patancheru≈ 38 min at peak19 min without traffic
Balanagar≈ 40 min at peak15 min without traffic
All 42 places
Moosapet≈ 41 min at peak16 min without traffic
Miyapur
Documents
Documents uploaded
233 of 241 document slotsFiled with TG-RERA
Document groups on the record
3 (7 documents)Filed with TG-RERA
Pictures and plans held
0
Task-by-task progress, dated certificates and changes between reads
Declared progress as declared by the builder to TG-RERA, not inspected
No overall figure filed for the project. The record files 328 building tables and no project figure; each is shown as filed, in the record's order, and none is averaged. Read from TG-RERA on 14/11/2026.
Building table 180%
Building table 280%
Building table 380%
Building table 480%
Building table 580%
Building table 680%
Building table 780%
Building table 880%
Building table 980%
Building table 1080%
Building table 1180%
Building table 1280%
Building table 1380%
Building table 1480%
Building table 1580%
Building table 1680%
Building table 1780%
Building table 1871%
Building table 1980%
Building table 2080%
Building table 2169.8%
Building table 2280%
Building table 2378.6%
Building table 2480%
Building table 2580%
Building table 2678.6%
Building table 2780%
Building table 2880%
Building table 2978.9%
Building table 3080%
Building table 3180%
Building table 3279.2%
Building table 3380%
Building table 3480%
Building table 3578.6%
Building table 3678.6%
Building table 3778.6%
Building table 3878.4%
Building table 3978.6%
Building table 4078.6%
Building table 4180%
Building table 4280%
Building table 4380%
Building table 4480%
Building table 4580%
Building table 4680%
Building table 4780%
Building table 4880%
Building table 490%
Building table 5078.6%
Building table 5178.6%
Building table 5278.6%
Building table 530%
Building table 5478.6%
Building table 5578.6%
Building table 5678.6%
Building table 5778.6%
Building table 5878.6%
Building table 5980%
Building table 6080%
Building table 6141.5%
Building table 6241.5%
Building table 630%
Building table 6411.5%
Building table 6511.5%
Building table 6678.6%
Building table 6778.6%
Building table 6878.6%
Building table 6980%
Building table 7080%
Building table 7180%
Building table 7278.6%
Building table 7380%
Building table 7478.6%
Building table 7578.6%
Building table 760%
Building table 7712%
Building table 7877.6%
Building table 7977.6%
Building table 8077.6%
Building table 8178.6%
Building table 8278.6%
Building table 8378.6%
Building table 8478.6%
Building table 8569.5%
Building table 8612%
Building table 8712%
Building table 8812%
Building table 8977.6%
Building table 9077.6%
Building table 9177.6%
Building table 9277.6%
Building table 9377.6%
Building table 9477.6%
Building table 9577.6%
Building table 9677.6%
Building table 9712%
Building table 9837%
Building table 9937%
Building table 10069.5%
Building table 10177.6%
Building table 10280%
Building table 10380%
Building table 10480%
Building table 10580%
Building table 10680%
Building table 10780%
Building table 10880%
Building table 10980%
Building table 11080%
Building table 11180%
Building table 11280%
Building table 11380%
Building table 11480%
Building table 11580%
Building table 11678.6%
Building table 11780%
Building table 11880%
Building table 11980%
Building table 12080%
Building table 12180%
Building table 12280%
Building table 12378.6%
Building table 12480%
Building table 12580%
Building table 12680%
Building table 12780%
Building table 12812.5%
Building table 1298%
Building table 1309%
Building table 13180%
Building table 13280%
Building table 13380%
Building table 13480%
Building table 13580%
Building table 13680%
Building table 13780%
Building table 13880%
Building table 13980%
Building table 14080%
Building table 1410%
Building table 1420%
Building table 1430%
Building table 1440%
Building table 14580%
Building table 14680%
Building table 14780%
Building table 14880%
Building table 14980%
Building table 15080%
Building table 15180%
Building table 15280%
Building table 15380%
Building table 15480%
Building table 15580%
Building table 1560%
Building table 15780%
Building table 15880%
Building table 15980%
Building table 16080%
Building table 16180%
Building table 16280%
Building table 16311.5%
Building table 1649%
Building table 16580%
Building table 16680%
Building table 16780%
Building table 16880%
Building table 16980%
Building table 17080%
Building table 17180%
Building table 17280%
Building table 17380%
Building table 17480%
Building table 17580%
Building table 17680%
Building table 17780%
Building table 17880%
Building table 17980%
Building table 18080%
Building table 18180%
Building table 18223%
Building table 18312%
Building table 18412%
Building table 18512%
Building table 18612%
Building table 18780%
Building table 18880%
Building table 18980%
Building table 19013%
Building table 19113%
Building table 19224%
Building table 19377.6%
Building table 19477.6%
Building table 19577.6%
Building table 19677.6%
Building table 19712%
Building table 19812%
Building table 19980%
Building table 20080%
Building table 20180%
Building table 20280%
Building table 20312%
Building table 20424%
Building table 20526.5%
Building table 20623%
Building table 20723%
Building table 20812%
Building table 20912%
Building table 2100%
Building table 21177.6%
Building table 21277.6%
Building table 21312%
Building table 21412%
Building table 2150%
Building table 2160%
Building table 2170%
Building table 2180%
Building table 2190%
Building table 22011.5%
Building table 22111.5%
Building table 2220%
Building table 22380%
Building table 22480%
Building table 22580%
Building table 22680%
Building table 22780%
Building table 22880%
Building table 22980%
Building table 2309.5%
Building table 23149%
Building table 23249%
Building table 23380%
Building table 23480%
Building table 23580%
Building table 23680%
Building table 23780%
Building table 23880%
Building table 23980%
Building table 24077.8%
Building table 24177.8%
Building table 24277.8%
Building table 24377.8%
Building table 24477.8%
Building table 24580%
Building table 24677.8%
Building table 24777.8%
Building table 24877.8%
Building table 24977.8%
Building table 2500%
Building table 25177.8%
Building table 25277.8%
Building table 25377.8%
Building table 25477.8%
Building table 25577.8%
Building table 25677.8%
Building table 25777.8%
Building table 25877.8%
Building table 25977.8%
Building table 26077.8%
Building table 26177.8%
Building table 2620%
Building table 26380%
Building table 26480%
Building table 26580%
Building table 26680%
Building table 26780%
Building table 26880%
Building table 26980%
Building table 27080%
Building table 27180%
Building table 27212%
Building table 2730%
Building table 27474%
Building table 27574%
Building table 27677.6%
Building table 27780%
Building table 27880%
Building table 27949%
Building table 28048.5%
Building table 28174%
Building table 28274%
Building table 28374%
Building table 28449%
Building table 28578.6%
Building table 28678.6%
Building table 28778.6%
Building table 28878.6%
Building table 28940.5%
Building table 29042.5%
Building table 29140.5%
Building table 29274%
Building table 29349%
Building table 29449%
Building table 2950%
Building table 29680%
Building table 29780%
Building table 29880%
Building table 29936%
Building table 3009%
Building table 3010%
Building table 3020%
Building table 3030%
Building table 3040%
Building table 3050%
Building table 3060%
Building table 3070%
Building table 3080%
Building table 3090%
Building table 3100%
Building table 3110%
Building table 3120%
Building table 3130%
Building table 3140%
Building table 3150%
Building table 3160%
Building table 3170%
Building table 3180%
Building table 3190%
Building table 3200%
Building table 3210%
Building table 3220%
Building table 3230%
Building table 3240%
Building table 3250%
Building table 3260%
Building table 3270%
Building table 32820.5%
Source: TG-RERA project record, construction table (Tasks / Activity), a web record, not a signed certificate. Dates: the date PropMap.ai read the record; the table gives no as-of date. Percentage of work, as declared by the builder; the total it is measured against is not stated. Covers: 328 building tables, no project figure filed.
No change between PropMap.ai's reads of 11/11/2026 and 14/11/2026 in the registration dates, completion date or declared work (58.8%).
Past the proposed completion date, not shown as completed
0
Shown as completed
0
TG-RERA complaint orders
Not counted
Not counted on this page, so this is not a count of zero. TG-RERA orders that name a project appear only in that project's Background Check report, after a compliance review.
A passed date does not mean a project is late or unfinished: the filings rarely record completion.
As declared to TG-RERA. The filing gives counts, not which flat is free, so confirm any flat with the builder. Of 170 other projects in Dundigal Gandimaisamma mandal with a booked count, 48 declare a larger share booked, 122 a smaller one and 0 the same, as last filed (records last updated 14/12/2018 to 13/11/2026; 1 carries no date).
330 units filed with TG-RERA without a bedroom type.
No price on record. PropMap.ai does not estimate prices. Type the builder's quote
What you type is kept on this device only and is not sent to PropMap.ai. PropMap.ai holds no price of its own: each figure below is an estimate from your quote and from the tax and duty rates listed with their sources.
Shamirpet (Genome Valley area)≈ 46 min at peak23 min without traffic
Kollur≈ 48 min at peak24 min without traffic
HITEC City≈ 50 min at peak18 min without traffic
Ameerpet≈ 54 min at peak19 min without traffic
Panjagutta≈ 54 min at peak21 min without traffic
Lingampally≈ 54 min at peak20 min without traffic
Raidurg (Mindspace)≈ 54 min at peak19 min without traffic
Kondapur≈ 57 min at peak20 min without traffic
Madhapur≈ 58 min at peak20 min without traffic
Begumpet≈ 60 min at peak21 min without traffic
Financial District≈ 60 min at peak26 min without traffic
Lakdikapul≈ 60 min at peak24 min without traffic
Kokapet≈ 61 min at peak29 min without traffic
Gachibowli≈ 61 min at peak23 min without traffic
Khajaguda≈ 61 min at peak24 min without traffic
DLF Cyber City, Gachibowli≈ 61 min at peak22 min without traffic
Nanakramguda (Waverock)≈ 62 min at peak29 min without traffic
Jubilee Hills≈ 63 min at peak22 min without traffic
Banjara Hills≈ 63 min at peak24 min without traffic
Narsingi≈ 66 min at peak28 min without traffic
Nampally station (Hyderabad Deccan)≈ 67 min at peak27 min without traffic
Abids≈ 68 min at peak27 min without traffic
Secunderabad Junction≈ 68 min at peak23 min without traffic
Mehdipatnam≈ 69 min at peak27 min without traffic
Koti≈ 70 min at peak28 min without traffic
Manikonda≈ 72 min at peak26 min without traffic
Pocharam (Infosys campus area)≈ 74 min at peak42 min without traffic
Kacheguda station≈ 76 min at peak29 min without traffic
Shamshabad≈ 76 min at peak39 min without traffic
Dilsukhnagar≈ 82 min at peak33 min without traffic
Uppal≈ 87 min at peak31 min without traffic
LB Nagar≈ 91 min at peak37 min without traffic
Rajiv Gandhi International Airport≈ 94 min at peak45 min without traffic
Adibatla (Aerospace SEZ area)≈ 103 min at peak53 min without traffic
How these are estimated
Peak: peak estimate: road-type speeds calibrated to TomTom Traffic Index 2025 for Hyderabad (about 15 km/h in the city); not live traffic, and a real rush hour can differ. Without traffic: free-flow estimate from OpenStreetMap roads (no traffic).
Chosen from public records by position, not ranked. Nobody can pay to appear here.
Filed documents and where each fact comes from
Filed by the builder on TG-RERA. Each link opens the copy held by the regulator, which may be slow or a scanned page. PropMap.ai links to these papers; it has not checked what they say.
RERA P02200006119 · by Aksara Constructions and Others · Bowrampet, Dundigal Gandimaisamma, 500043
Built by rule from this project's TG-RERA record, read by PropMap.ai on 14/11/2026. Figures are as the builder declared them. The marks and notes are the buyer's own.
Your marks stay on this device. What you mark, the date and your note are not sent to PropMap.ai or to anyone else, and they are lost if this browser's data is cleared. PropMap.ai counts that a mark was made on this project, never what it says. PropMap.ai arranges no visit and sends nothing to the builder.
10 items, none marked yet.
Ask the builder for
On recordRegistration is current until 30/08/2028
Ask for: the possession date, written into the draft of your agreement.Question: “Does the possession date in my agreement fall before 30/08/2028, when the registration ends?” See the registration dates
Asked SeenDate: Note:
An approval paper is filed on TG-RERA; its number is not stated
Ask for: the approval number, and the approved plan that carries it.Question: “What is the approval number, and does the plan show my tower and my floor?” See approvals
Asked SeenDate: Note:
On recordThe builder declared 27 of 330 homes booked (record last updated 30/04/2026)
Ask for: the list of unsold homes of the type you want, with floor and facing.Question: “Which homes of my type are unsold today?” See the booked count
Asked SeenDate: Note:
PropMap.ai holds no prices
Ask for: the all-in cost in writing: the price, every other charge, taxes and registration costs, line by line.Question: “What is the total I will pay for this flat, with every charge and tax listed?”
Asked SeenDate: Note:
35 title files are uploaded to TG-RERA; PropMap.ai has not read them
Ask for: copies of the title papers for the land, for your lawyer to read. PropMap.ai does not check title: no flag found is not a clear title.Question: “May my lawyer have copies of the title papers, and of any loan or claim on the land?” See the filed title papers
Asked SeenDate: Note:
Look at on site (5)
On recordRERA number on record: P02200006119
Look at: the registration number printed on the site board, the brochure and any receipt.Question: “Is P02200006119 the number on everything you give me?”
Asked SeenDate: Note:
ConstructionThe filing shows 327 buildings
Look at: how many buildings stand, and the floor the structure has reached in yours. Take dated photos.Question: “Which floor has the structure reached in my tower?” See the filed buildings
Asked SeenDate: Note:
The filing lists 11 common facilities
Look at: which of them exist today, such as roads, water supply, drains and open space.Question: “Which shared facilities are finished, and when will the rest be?” See the filed facilities
Asked SeenDate: Note:
PropMap.ai's map position for this project is approximate
Look at: the exact entrance, and what stands on each side of the site.Question: “Is this the plot in the registration, and what is planned on the land next to it?” See the location
Asked SeenDate: Note:
Drive times on this page are estimates, not measured traffic
Look at: the drive to your daily destination, timed by you at the hour you would travel.Question: “Which road do residents take at peak hour?” See the estimates
Asked SeenDate: Note:
Is this home right for you? Four questions, kept on this device
Is this home right for you?
Answer four questions once, and each project says in words which of your needs its record meets. Kept on this device only.
Approximate position: placed from the registered address, not the site itself. In our check 4 in 5 such positions were within about 2.5 km, and a few were over 5 km off.
Labels: Filed with TG-RERA (the builder's filing or the regulator's record), Builder's site says, Measured from open map data, Conflict, Not known. A filing and the builder's own site agreeing does not prove a figure: both come from the builder.