Source: Telangana Real Estate Regulatory Authority (TG-RERA), rera.telangana.gov.in. Reproduced as published; fetched 24/11/2026. The records compared above were read from 14/11/2026 to 24/11/2026. PropMap.ai reports what public records say. It is not legal advice.
Pragathi S Raghupathi County
Registration. The registration was valid until 04/01/2026, a date that has passed. TG-RERA listed no extension certificate when PropMap.ai read this project on 24/11/2026. Ask for: the extension order, or the occupancy certificate if the project is finished.
Worked out by PropMap.ai from the dates on this page.
Completion. The completion date the builder first filed, 04/01/2026, has passed, and the project status on TG-RERA still reads "New Project" (read 24/11/2026). Ask for: the occupancy certificate, or the revised completion date.
Worked out by PropMap.ai from the dates on this page.
Orders and complaints are not shown on this page. TG-RERA orders that name this project appear only in its Background Check report, after a compliance review, with the sources searched and their dates.
Drive times, places nearby and other projects within 5 km
Drive times
Approximate position: placed from the registered address, not the site itself. In our check 4 in 5 such positions were within about 4 km, and a few were over 5 km off.
Kukatpally≈ 25 min at peak11 min without traffic
Balanagar≈ 30 min at peak13 min without traffic
Miyapur≈ 31 min at peak12 min without traffic
All 42 places
Moosapet≈ 32 min at peak14 min without traffic
HITEC City≈ 40 min at peak
Documents
Documents uploaded
30 of 36 document slotsFiled with TG-RERA
Document groups on the record
3 (9 documents)Filed with TG-RERA
Pictures and plans held
0
Task-by-task progress, dated certificates and changes between reads
Declared progress as declared by the builder to TG-RERA, not inspected
No overall figure filed for the project. The record files 9 building tables and no project figure; each is shown as filed, in the record's order, and none is averaged. Read from TG-RERA on 24/11/2026.
Building table 181.6%
Building table 281.6%
Building table 381.6%
Building table 481.6%
Building table 581.6%
Building table 681.6%
Building table 781.6%
Building table 881.6%
Building table 981.6%
Source: TG-RERA project record, construction table (Tasks / Activity), a web record, not a signed certificate. Dates: the date PropMap.ai read the record; the table gives no as-of date. Percentage of work, as declared by the builder; the total it is measured against is not stated. Covers: 9 building tables, no project figure filed.
Not counted on this page, so this is not a count of zero. TG-RERA orders that name a project appear only in that project's Background Check report, after a compliance review.
A passed date does not mean a project is late or unfinished: the filings rarely record completion.
As declared to TG-RERA. The filing gives counts, not which flat is free, so confirm any flat with the builder. Of 130 other projects in Bachupally mandal with a booked count, 51 declare a larger share booked, 0 a smaller one and 79 the same, as last filed (records last updated 09/01/2019 to 30/10/2026).
Home types
Type
Homes
Not booked
Saleable size
2 BHK
287
287
1,265 to 1,325 sq ft
3 BHK
294
294
1,505 to 2,075 sq ft
Saleable area, not carpet area. Ask for the carpet area in writing. 4 other units are filed without a bedroom type, such as clubhouses or shops.
No price on record. PropMap.ai does not estimate prices. Type the builder's quote
What you type is kept on this device only and is not sent to PropMap.ai. PropMap.ai holds no price of its own: each figure below is an estimate from your quote and from the tax and duty rates listed with their sources.
Towers, floor by floor (9)
booked not booked, as declared.
BHOOMI7 floors with homes · 8 slabs filed · 1 basement · 56 homes, 0 booked
70 of 8
60 of 8
50 of 8
40 of 8
30 of 8
20 of 8
15 min without traffic
Ameerpet≈ 44 min at peak19 min without traffic
Lingampally≈ 44 min at peak17 min without traffic
Panjagutta≈ 44 min at peak19 min without traffic
Raidurg (Mindspace)≈ 45 min at peak17 min without traffic
Patancheru≈ 46 min at peak21 min without traffic
Kondapur≈ 47 min at peak17 min without traffic
Madhapur≈ 48 min at peak18 min without traffic
Lakdikapul≈ 50 min at peak22 min without traffic
Jeedimetla≈ 51 min at peak18 min without traffic
Begumpet≈ 52 min at peak22 min without traffic
Tellapur≈ 53 min at peak25 min without traffic
DLF Cyber City, Gachibowli≈ 53 min at peak19 min without traffic
Jubilee Hills≈ 53 min at peak20 min without traffic
Banjara Hills≈ 53 min at peak23 min without traffic
Gachibowli≈ 56 min at peak20 min without traffic
Shamirpet (Genome Valley area)≈ 56 min at peak28 min without traffic
Kompally≈ 56 min at peak19 min without traffic
Kollur≈ 56 min at peak26 min without traffic
Nampally station (Hyderabad Deccan)≈ 57 min at peak25 min without traffic
Khajaguda≈ 58 min at peak21 min without traffic
Abids≈ 58 min at peak25 min without traffic
Financial District≈ 59 min at peak23 min without traffic
Mehdipatnam≈ 59 min at peak26 min without traffic
Koti≈ 61 min at peak26 min without traffic
Secunderabad Junction≈ 63 min at peak24 min without traffic
Narsingi≈ 65 min at peak25 min without traffic
Manikonda≈ 65 min at peak24 min without traffic
Nanakramguda (Waverock)≈ 65 min at peak26 min without traffic
Kacheguda station≈ 66 min at peak28 min without traffic
Kokapet≈ 67 min at peak26 min without traffic
Dilsukhnagar≈ 73 min at peak32 min without traffic
Shamshabad≈ 80 min at peak36 min without traffic
LB Nagar≈ 81 min at peak36 min without traffic
Uppal≈ 82 min at peak32 min without traffic
Pocharam (Infosys campus area)≈ 84 min at peak45 min without traffic
Rajiv Gandhi International Airport≈ 98 min at peak42 min without traffic
Adibatla (Aerospace SEZ area)≈ 112 min at peak52 min without traffic
How these are estimated
Peak: peak estimate: road-type speeds calibrated to TomTom Traffic Index 2025 for Hyderabad (about 15 km/h in the city); not live traffic, and a real rush hour can differ. Without traffic: free-flow estimate from OpenStreetMap roads (no traffic).
Chosen from public records by position, not ranked. Nobody can pay to appear here.
Filed documents and where each fact comes from
Filed by the builder on TG-RERA. Each link opens the copy held by the regulator, which may be slow or a scanned page. PropMap.ai links to these papers; it has not checked what they say.
RERA P02200001791 · by Pragathi Infra · BACHUPALLY, 500090
Built by rule from this project's TG-RERA record, read by PropMap.ai on 24/11/2026. Figures are as the builder declared them. The marks and notes are the buyer's own.
Your marks stay on this device. What you mark, the date and your note are not sent to PropMap.ai or to anyone else, and they are lost if this browser's data is cleared. PropMap.ai counts that a mark was made on this project, never what it says. PropMap.ai arranges no visit and sends nothing to the builder.
12 items, none marked yet.
Ask the builder for
RegistrationRegistration ended on 04/01/2026
Ask for: the paper that extends the registration beyond that date, or the paper that certifies the project as complete.Question: “The registration has ended. Which paper extends it or closes it, and may I see it?” See the registration dates
Asked SeenDate: Note:
CompletionThe declared completion date (04/01/2026) has passed
Ask for: the new completion date in writing and, if it exists, the paper that allows people to move in.Question: “What is the new completion date, and has permission to occupy been given for my block?” See declared progress
Asked SeenDate: Note:
On recordApproval number 021391/MED/R1/U6/HMD is declared to TG-RERA
Ask for: the approved plan that carries this number, showing your tower and floor.Question: “Does the approved plan with this number show my tower, my floor and the flat as offered?” See approvals
Asked SeenDate: Note:
On recordThe builder declared 0 of 585 homes booked (record last updated 16/05/2025)
Ask for: the list of unsold homes of the type you want, with floor and facing.Question: “Which homes of my type are unsold today?” See the booked count
Asked SeenDate: Note:
Filed sizes (1,265 to 2,075 sq ft) are saleable area, not carpet area
Ask for: the carpet area of the flat offered, in writing, and the same figure in the agreement.Question: “What is the carpet area of this flat, and which figure will the agreement carry?” See the filed sizes
Asked SeenDate: Note:
PropMap.ai holds no prices
Ask for: the all-in cost in writing: the price, every other charge, taxes and registration costs, line by line.Question: “What is the total I will pay for this flat, with every charge and tax listed?”
Asked SeenDate: Note:
18 title files are uploaded to TG-RERA; PropMap.ai has not read them
Ask for: copies of the title papers for the land, for your lawyer to read. PropMap.ai does not check title: no flag found is not a clear title.Question: “May my lawyer have copies of the title papers, and of any loan or claim on the land?” See the filed title papers
Asked SeenDate: Note:
Look at on site (5)
On recordRERA number on record: P02200001791
Look at: the registration number printed on the site board, the brochure and any receipt.Question: “Is P02200001791 the number on everything you give me?”
Asked SeenDate: Note:
ConstructionThe filing shows 8 buildings, the tallest with 7 floors of homes
Look at: how many buildings stand, and the floor the structure has reached in yours. Take dated photos.Question: “Which floor has the structure reached in my tower?” See the filed buildings
Asked SeenDate: Note:
The filing lists 12 common facilities
Look at: which of them exist today, such as roads, water supply, drains and open space.Question: “Which shared facilities are finished, and when will the rest be?” See the filed facilities
Asked SeenDate: Note:
PropMap.ai's map position for this project is approximate
Look at: the exact entrance, and what stands on each side of the site.Question: “Is this the plot in the registration, and what is planned on the land next to it?” See the location
Asked SeenDate: Note:
Drive times on this page are estimates, not measured traffic
Look at: the drive to your daily destination, timed by you at the hour you would travel.Question: “Which road do residents take at peak hour?” See the estimates
Asked SeenDate: Note:
Is this home right for you? Four questions, kept on this device
Is this home right for you?
Answer four questions once, and each project says in words which of your needs its record meets. Kept on this device only.
1
0 of 8
PRUDHVI7 floors with homes · 8 slabs filed · 1 basement · 77 homes, 0 booked
70 of 11
60 of 11
50 of 11
40 of 11
30 of 11
20 of 11
10 of 11
MAHI7 floors with homes · 8 slabs filed · 1 basement · 77 homes, 0 booked
70 of 11
60 of 11
50 of 11
40 of 11
30 of 11
20 of 11
10 of 11
BHUVI7 floors with homes · 8 slabs filed · 1 basement · 63 homes, 0 booked
70 of 9
60 of 9
50 of 9
40 of 9
30 of 9
20 of 9
10 of 9
AVANI7 floors with homes · 8 slabs filed · 1 basement · 77 homes, 0 booked
70 of 11
60 of 11
50 of 11
40 of 11
30 of 11
20 of 11
10 of 11
ACHALA7 floors with homes · 8 slabs filed · 1 basement · 77 homes, 0 booked
70 of 11
60 of 11
50 of 11
40 of 11
30 of 11
20 of 11
10 of 11
URVI7 floors with homes · 8 slabs filed · 1 basement · 77 homes, 0 booked
70 of 11
60 of 11
50 of 11
40 of 11
30 of 11
20 of 11
10 of 11
DHATRI7 floors with homes · 8 slabs filed · 1 basement · 77 homes, 0 booked
70 of 11
60 of 11
50 of 11
40 of 11
30 of 11
20 of 11
10 of 11
AMENITIES BLOCK4 slabs filed · 1 basement
The site: land, built-up area, survey number
Land
7.50 acres
Approved built-up area
8,93,364 sq ft
Buildings on the approved plan
9
Towers with homes
8
Highest floor with homes
7 floors
Lost to road widening or a lake's full tank level
None filed
Survey number
148/B
Site boundaries
east
SURVEY NO 148 A
west
20 FT WIDE APPROACH ROAD (name withheld) FROM SY 148 B
north
LAND BELONGING TO (name withheld) AND (name withheld)
south
SURVEY NO 146
Filed with TG-RERA. People's names are withheld.
Common facilities filed with TG-RERA (14)
Internal Roads & Footpaths90% declared
Water Supply100% declared
Sewerage (Chamber, Lines, Septic Tank , STP)90% declared
Storm Water Drains70% declared
Green Strip/TOT LOT/Park60% declared
Street Lighting75% declared
Community BuildingsNot provided
Treatment And Disposal Of Sewage And Sullage Water90% declared
Solid Waste Management And Disposal70% declared
Water Conservation, Rain water Harvesting60% declared
Energy management75% declared
Fire Protection And Fire Safety Requirements90% declared
Electrical Meter Room, Sub-Station, Receiving Station70% declared
Aggregate area of recreational Open SpaceNot provided
This project's position is approximate: it was placed from the registered address and may be over 2 km from the site. Distances here are measured from that position, so treat them as approximate too.
Approximate position: may be over 2 km off, so distances are approximate too.